Kenner, LA Hurricane Preparedness: Flood Elevation (2026)
Key Facts
- Equipment freeboard
- 2 feet above base flood elevation
- New addition floor
- 2 feet above base flood elevation, all HVAC
- Certification required
- Registered engineer, architect, or land surveyor
- Applies in
- Zones AE, VE and local flood hazard zones
- Max penalty
- $500 fine, 60 days jail, Sec. 1-9
Summary
In flood hazard areas across Kenner, new construction and substantial improvements must meet the elevation standards of Code of Ordinances Sec. 5-182: mechanical, electrical, and HVAC equipment, and the lowest floor of new horizontal additions, must sit at least two feet above the base flood elevation to keep systems safe from storm flooding.
In all areas of special flood hazards (zone AE and VE) and areas of local flood hazard (zone X, X-Protected by Levee, and 0.2% Annual Chance), the following higher regulatory provisions for permits are required for all new construction and substantial damage/improvement (as further denied below) to ensure sites are reasonably safe from flooding. ... (4)Electrical, heating, ventilation, plumbing, air conditioning equipment and other service facilities shall be designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding, such facilities shall be located a minimum of two (2) feet above the base flood elevation.(5)All new horizontal additions must have the lowest floor and all HVAC shall be located a minimum of two (2) feet above the base flood elevation.
Full Breakdown
Sec. 5-182 sets the elevation standards that apply in both the special flood hazard areas, zones AE and VE, and the local flood hazard zones X, X-Protected by Levee, and 0.2% Annual Chance, for all new construction and substantial damage or improvement. A registered professional engineer, architect, or land surveyor must certify to the Department of Inspection and Code Enforcement that a project meets the standard. Beyond the general anchoring and flood-resistant-materials rules that apply chapterwide, Sec. 5-182 raises the bar for building systems specifically: electrical, heating, ventilation, plumbing, and air conditioning equipment and other service facilities must be designed or located so water cannot enter or accumulate in them during flooding, and must sit at least two feet above the base flood elevation. Any new horizontal addition must have its lowest floor and all HVAC equipment at that same two-foot freeboard above the base flood elevation.
The floodplain administrator, working with the Department of Inspection and Code Enforcement, reviews and certifies compliance under Sec. 5-171, and can require additional base flood elevation data when FEMA has not supplied it for a site. Because Kenner sits low relative to Lake Pontchartrain and the Mississippi River levee system, this two-foot equipment and addition freeboard is meant to keep home systems functioning through the storm surge flooding a hurricane can push into the city.
Violations & Fines
Sec. 5-195 punishes any owner, contractor, architect, or other person who violates the elevation standards, or who maintains a building where the violation exists, as provided in Sec. 1-9: a fine of up to five hundred dollars, up to sixty days in jail, or both, with each day the violation continues treated as a separate offense.
Frequently Asked Questions
How high above flood level must my HVAC unit sit in Kenner?
Does a new room addition need to meet a flood elevation standard?
Who has to certify that my project meets the elevation standard?
Sources & Official References
Other rules in Kenner
Compare Kenner to another location·View the Louisiana hurricane preparedness overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.