Berwyn, IL Sidewalk & Pedestrian Rules: Encroachment Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
Director of Public Works, on written application
Maximum duration
No more than 90 days
Roadway limit
Material storage cannot exceed one-third of roadway width
Curb clearance
At least one foot between obstruction and curb line
Sidewalk clearance
At least six feet kept open and unobstructed
Fine
Up to $2,000 per violation under § 202.99, each day separate

Summary

In the City of Berwyn, Illinois, no one can store building materials or equipment on a street, alley, parkway or sidewalk without written permission from the Director of Public Works. Permission runs at most 90 days, and a sidewalk at least six feet wide must stay open.

§ 1020.01 TEMPORARY USE OF STREETS; PERMITS; LIMITATIONS. ... (A) A person who wishes to use a public street, roadway, court, alley or parkway in the city for the purpose of storing or depositing any building material, machinery, tool, tool box, tool shed, fuel or other supply, for any building or structure in the course of being constructed, moved, altered or repaired, shall first make application in writing to the Director of Public Works for permission to do so. ... No permission shall be granted for a period longer than 90 days. ... (C) The occupation of the sidewalk or street for the storage of building material shall not exceed one-third of the width of the roadway, and in all cases where the obstruction of the street is made, there shall be a clear space of not less than one foot between the obstruction and the curb line. ... During the progress of building operations, a sidewalk not less than six feet in width shall be at all times kept open and unobstructed for the purpose of passage in front of the lot.

Full Breakdown

Section 1020.01 of the Berwyn Code of Ordinances governs temporary private use of the public right-of-way for construction. A person who wants to use a public street, roadway, court, alley or parkway to store or deposit building material, machinery, tools, a tool shed, fuel or other supplies for a building being constructed, moved, altered or repaired must first apply in writing to the Director of Public Works. The application describes the location to be occupied, the use to be made of it, and how long the occupation will last.

Approval is discretionary. The Director grants permission only if the applicant has complied with the chapter and the city's building ordinances on bonds, fees and other requisites. Permission is meant only for imperative use in connection with actual erection, repair, alteration, wrecking or removal of buildings, ends when the work is complete or earlier if the Director requires, and cannot run longer than 90 days.

The permit carries physical limits. Storing building material cannot take up more than one-third of the width of the roadway, and a clear space of at least one foot must remain between the obstruction and the curb line. The permit covers only the frontage immediately in front of the lot where the building is under construction. During building operations a sidewalk not less than six feet wide must stay open and unobstructed for passage in front of the lot, and where excavations sit beside the sidewalk it must be protected by substantial railings for as long as the excavations remain. Under subsection (B), no one can occupy a sidewalk or street after the permitted operation is finished or store articles not intended for immediate use.

Related rules apply. Section 1020.03 requires yellow lanterns overnight at each end of a pile of material or an excavation in a street or alley. Section 440.03 bars anyone from obstructing or encroaching upon any public highway, street, alley or commons. Utilities building facilities in the right-of-way need a separate Building Department permit under § 1010.04, and in the C-1 through C-4 districts balconies and bay windows can project over the city right-of-way only with Zoning Administrator approval (§ 1246.14).

Violations & Fines

Chapter 1020 has no specific penalty clause. Section 1020.99 refers to the general penalty in § 202.99, which sets a fine of not more than $2,000 for each violation, with every day the violation continues counting as a separate offense. Occupying a sidewalk or street after the permitted work ends, or without a permit, falls under that fine schedule.

Frequently Asked Questions

Who issues a permit to use a Berwyn street or sidewalk for construction storage?
The Director of Public Works. Section 1020.01(A) requires a written application describing the street, roadway, court, alley or parkway to be occupied, the use, and the length of time. The Director grants permission only if bonds, fees and other requirements of the city's building ordinances are met.
How long can a Berwyn street occupancy permit last?
No more than 90 days. The permission also ends when the operation is complete, or earlier if the Director finds it feasible and requires. After that, § 1020.01(B) prohibits occupying the sidewalk or street, and stored articles must be intended for immediate use in the permitted work.
How much sidewalk must stay open during construction in Berwyn?
A sidewalk not less than six feet in width must be kept open and unobstructed in front of the lot at all times during building operations. If there are excavations beside it, substantial railings must protect the sidewalk for as long as the excavations exist (§ 1020.01(C)).
Can I stack materials across the whole street frontage?
No. Storage of building material cannot exceed one-third of the roadway width, and one foot must remain clear between the obstruction and the curb line. The permit covers only the space immediately in front of the lot where the building is being erected and for which the permit was issued.

Sources & Official References

Other rules in Berwyn

All Berwyn rules

Compare Berwyn to another location·View the Illinois sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Berwyn, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in Cook County handle encroachment permits.

Arlington Heights, IL
Some Restrictions
Oak Park, IL
Some Restrictions
Chicago, IL
Some Restrictions
Skokie, IL
Significant Restrictions
Tinley Park, IL
Significant Restrictions
Evanston, IL
Significant Restrictions
Oak Lawn, IL
Significant Restrictions