Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Bossier Parish Code § 19-5(a)
Small-structure exemption
Accessory bldgs under 200 sq ft
Fence exemption
Fences 6 ft or shorter
Application abandoned
180 days with no action
Penalty
$100-$500 fine per offense, Sec. 19-14

Summary

Code Section 19-5 makes it unlawful to construct, enlarge, alter, move, demolish or change the occupancy of any building or structure in unincorporated Bossier Parish, or to install a regulated electrical, gas, mechanical or plumbing system, without a permit from the Bossier Parish Building Official.

These county ordinances apply to unincorporated areas of Bossier Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(a)Required. It shall be unlawful to construct, enlarge, alter, extensively alter, repair, move, demolish, or change the occupancy of any building or structure, or to erect, install, enlarge, alter, extensively alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by the technical codes adopted in section 19-3, or to cause any such work to be done, without obtaining a properly issued permit from the Bossier Parish Building Official for that work

Full Breakdown

Section 19-5(a) of the Bossier Parish Code states plainly that it is unlawful to construct, enlarge, alter, extensively alter, repair, move, demolish, or change the occupancy of any building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system regulated by the technical codes adopted in Section 19-3, without first obtaining a properly issued permit from the Bossier Parish Building Official. Section 19-5(c) through (j) then lists specific work exempt from that requirement: one-story detached accessory structures without utilities under 200 square feet, fences no taller than six feet, retaining walls no taller than four feet measured from footing to top, water tanks up to 5,000 gallons, sidewalks and driveways, finish work like painting and tiling, swimming pools less than 24 inches deep, playground equipment, and window awnings that project no more than 54 inches.

To apply, Section 19-5(k)-(l) requires a written application on the Building Department's form identifying the work, describing the property by legal description or address, stating the construction valuation, and, for larger projects, naming the owner and all contractors. The building official examines the application within a reasonable time and must reject it in writing with reasons if it does not conform to the code; if it does, the official issues the permit as soon as practicable. Under Section 19-5(n) and (p), an unpursued application is deemed abandoned after 180 days, and an issued permit becomes invalid if work is not started within 180 days or is suspended for 180 days, though the building official can grant extensions for justified cause. The permit or a copy must be posted and visible at the front exterior of the job site until the project is complete.

Violations & Fines

Doing regulated construction, alteration, demolition or system work without the required permit violates Section 19-5 and Section 19-12; the Bossier Parish Building Official can issue a stop-work order under Section 19-13, and violators face a misdemeanor fine of not less than $100.00 nor more than $500.00 per offense under Section 19-14, plus the parish attorney may seek an injunction.

Frequently Asked Questions

When do I need a building permit in unincorporated Bossier Parish?
Section 19-5(a) requires a permit from the Bossier Parish Building Official before you construct, enlarge, alter, move, demolish or change the occupancy of any building or structure, or install a regulated electrical, gas, mechanical or plumbing system.
Do I need a permit for a small storage shed or fence?
No. Section 19-5(c) exempts one-story detached accessory structures without utilities under 200 square feet, and fences no taller than six feet, from the building permit requirement, along with sidewalks, driveways and similar minor work.
How long do I have to start work after getting a Bossier Parish permit?
Section 19-5(p) voids the permit if work is not started within 180 days of issuance, or if it is suspended or abandoned for 180 days after starting, though the building official can grant extensions for justified cause.
What happens if I never pull the permit I applied for?
Section 19-5(n) treats an application as abandoned 180 days after filing unless you have pursued it in good faith or the permit was issued, though the building official can grant one or more 180-day extensions for justified cause.

Sources & Official References

Other rules in Bossier Parish

All Bossier Parish rules

Compare Bossier Parish to another location·View the Louisiana building safety overview

Get notified when Building Permits in Bossier Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.