Bossier Parish, LA Building Safety: Building Inspections (2026)
Key Facts
- Governing section
- Bossier Parish Code § 19-9
- Foundation inspection
- Before concrete is poured
- Rough-in inspection
- Before plumbing/mechanical/electrical covered
- Third-party report deadline
- 3 days after inspection
- Final inspection
- Required before occupancy
Summary
In unincorporated Bossier Parish, Code Section 19-9 requires permitted construction to stay accessible for inspection at every stage: foundation, rough plumbing/mechanical/electrical, framing and masonry, and a final inspection before occupancy, all performed or accepted by the Bossier Parish Building Official or a certified third-party provider.
A.Residential.(1)General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... (i)Foundation inspection. Inspection of the foundation shall be made after poles or piers are set or trenches or basement areas are excavated and any required forms erected and any required reinforcing steel is in place and supported prior to the placing of concrete. ... (vii)Final inspection. Final inspection shall be made after the permitted work is complete and prior to occupancy.
Full Breakdown
Section 19-9 of the Bossier Parish Code sets the inspection sequence the Bossier Parish Building Official follows for both residential and nonresidential construction outside the municipalities. Work covered by a permit must remain accessible and exposed for inspection until approved, and the permit holder is responsible for keeping it that way; the building official is not liable for costs incurred to expose work for inspection. Before a permit issues, the building official may conduct a preliminary inspection of the site. Once construction starts, the code calls out a series of required inspections: a foundation inspection after piers or trenches are excavated and any reinforcing steel is set but before concrete is poured; a rough inspection of plumbing, mechanical, gas and electrical systems before they are covered, with an exception for ground-source heat pump loop systems that have already been pressure tested; a frame and masonry inspection after the roof, framing, firestopping and bracing are up and the rough trades are approved; a fire-resistance-rated construction inspection where required between dwelling units, made after lathing or wallboard is up but before plaster or taping; and a final inspection made after all permitted work is complete and before occupancy.
For nonresidential projects, Section 19-9(b) adds footing and foundation, concrete slab and under-floor, framing, lath and gypsum board, fire-resistant penetration and energy-efficiency inspections. The building official may accept reports from state-certified third-party providers, who must submit their reports within three days of completing an inspection, with the final inspection report required before a certificate of occupancy can issue. Work may not proceed past a failed or unrequested inspection point without the building official's approval, and any noncompliant portion must be corrected before it is covered again.
Violations & Fines
Covering or concealing work before the required inspection is approved, or proceeding past a failed inspection point without correction, violates Section 19-9 and Section 19-12; violators are subject to a stop-work order under Section 19-13 and a misdemeanor fine between $100.00 and $500.00 per offense under Section 19-14.
Frequently Asked Questions
When does the building official inspect my foundation in Bossier Parish?
Can a certified inspector other than the parish do my inspections?
What is the last inspection before I can occupy a new building?
Sources & Official References
Other rules in Bossier Parish
Compare Bossier Parish to another location·View the Louisiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.