Coconut Creek, FL Building Safety: Building Permits (2026)
Key Facts
- Permit issuer
- Director of sustainable development
- Who can apply
- Owner, or licensed bonded contractor
- Plans required
- Two sets plus a registered land surveyor's survey
- Permit expiration
- 180 days if construction does not commence
- Minimum fee
- $75.00, non-refundable (Sec. 13-84)
- Penalty
- Section 1-8, each day a separate offense
Summary
In the City of Coconut Creek, Florida, a building permit is required for construction, addition, alteration, movement, repair or change of use of any building, structure or land. Only the owner or a licensed, bonded contractor can apply, and a permit expires if work does not start within 180 days.
(a)Required. ... A building permit is required for construction, addition, alteration, movement, repair or change to a new or different use of any building, structure or land. A permit is also required for all work by city franchises and their assigns within the city limits, rights-of-way and easements granted to the city. ... Applications will-only be accepted from the property owner or a licensed, bonded contractor representing the property owner. ... (3)All building and construction permits shall expire if construction does not commence within one hundred eighty (180) days from the date of issuance.
Full Breakdown
Section 13-38 of the Coconut Creek Code opens with a broad trigger: a building permit is required for construction, addition, alteration, movement, repair or change to a new or different use of any building, structure or land. It also applies to all work by city franchises and their assigns within the city limits, rights-of-way and easements granted to the city.
Applications go to the department of sustainable development. They must contain the information the director of sustainable development requires under the Florida Building Code, be accompanied by a survey prepared by a registered land surveyor of the state, and include the processing fees set by division 4 of the article. Applications are accepted only from the property owner or a licensed, bonded contractor representing the owner. Completed forms are submitted with two sets of construction plans, reviewed by the department, then returned for correction or approved, and the director authorizes issuance after all required approvals.
The director cannot issue a permit unless the work conforms to the Land Development Code and the Florida Building Code. A permit for a principal building also needs a plat approved by the city commission and recorded in the county's official records after June 4, 1953, with exceptions for a single-family dwelling on a qualifying parcel and for multifamily or nonresidential parcels under five acres delineated on a recorded plat. Where these requirements conflict with other state and county regulations, the most restrictive applies.
All building and construction permits expire if construction does not begin within 180 days of issuance. A permit authorizes only the use, arrangement and construction shown on approved plans, and a permit issued in error confers no rights and is null and void.
Fees come from section 13-84 and are non-refundable: a $75.00 minimum, 2.0 percent of construction cost for new residential work, 2.5 percent for new commercial work, and 4.0 percent (residential) or 4.5 percent (commercial) of cost with a $300.00 minimum for renovations. Fences are $0.75 per lineal foot, walls $2.00 per lineal foot, sheds and carports $100.00, demolition $100.00 and swimming pools or spas $700.00.
Violations & Fines
Under section 13-38(d)(4), use, arrangement or construction that deviates from approved plans is a violation of the chapter. Under section 13-38(d)(5), any person in violation is punished pursuant to section 1-8, and each day on which a violation is committed or permitted to continue is a separate offense punishable as such.
Frequently Asked Questions
When do I need a building permit in the City of Coconut Creek?
Who can apply for a building permit?
How long is a Coconut Creek building permit good for?
How much does a building permit cost?
Sources & Official References
Other rules in Coconut Creek
Florida rules heatmap·Compare Coconut Creek to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Broward County handle building permits.