Permit required for
Construction, demolition, alteration, use change
Permit validity
2 years from issuance
Extension fee
Half original fee, then quarter fee
Application review time
1 month from complete application
Maximum fine
$5,000 plus up to 15 days jail
Appeal deadline
60 days to Board of Appeals

Summary

Ramapo requires a building permit for construction, reconstruction, moving, demolition, structural alteration or any change in use of a building, plus any change in bulk unless the work qualifies as an ordinary repair. Applications go to the Building Inspector with plans, fees and a Standard Schedule of Fees payment.

A building permit is required for: A. The construction, reconstruction, moving, demolition, structural alteration or change in the use of a building or a structure. B. Any change in the bulk of a building, structure, or nonbuilding use, but not including ordinary repairs, provided that such repairs do not involve: (1) The removal or cutting away of a load-bearing wall, partition, or portion thereof, or of any structural beam or load-bearing component; (2) The removal or change of any required means of egress, or the rearrangement of parts of a structure in a manner which affects egress; (3) The enlargement, alteration, replacement or relocation of any building system; (4) The removal from service of all or part of a fire protection system for any period of time.

Full Breakdown

Town Code § 376-144 requires a building permit for the construction, reconstruction, moving, demolition, structural alteration or change in use of a building or structure, and for any change in the bulk of a building, structure or nonbuilding use. Ordinary repairs are exempt only if they do not involve removing or cutting a load-bearing wall, partition or structural beam; removing or changing a required means of egress; enlarging, altering, replacing or relocating a building system; or taking a fire protection system out of service, per § 376-144B.

Under § 376-145, applications go to the Building Inspector on the Town's forms and must include a Tax Map description of the parcel, the proposed use, the valuation of the work, the owner's and applicant's names and addresses, plans and specifications bearing the seal of a licensed architect or engineer, and a fee under the Standard Schedule of Fees. The Building Inspector must approve or disapprove within one month of receiving a complete application, and one set of approved plans must stay on site during construction.

Section 376-146 sets every permit to expire two years from issuance; if work has started but is unfinished, the holder may get a one-year extension from the Building Inspector for half the original fee, and a second one-year extension for a quarter of the fee. If work never started, the Board of Appeals can grant a one-year extension for half the fee. Section 376-147 lets the Building Inspector revoke a permit for false statements, permit issued in error, failure to follow an approved site plan, work that departs from the approved plans, or ignoring a stop-work order issued under § 376-148.

No building permit or certificate of occupancy may issue unless the work conforms to this chapter, the New York State Uniform Fire Prevention and Building Code and the State Energy Conservation Construction Code, per § 376-142.

Violations & Fines

Violating § 376-144 or building without a valid permit is enforced under § 376-1413: a fine up to $5,000, imprisonment up to 15 days, or both, with each day the violation continues counted as a separate offense. The Building Inspector may also issue a stop-work order under § 376-148 and revoke the permit if work continues in defiance of it. Decisions of the Building Inspector are appealable to the Board of Appeals within 60 days under § 376-1415.

Frequently Asked Questions

Does every home repair in Ramapo need a building permit?
No. Ordinary repairs are exempt under § 376-144B unless they remove or cut a load-bearing wall or structural beam, change a required means of egress, alter a building system, or take a fire protection system out of service. Anything beyond that scope needs a permit from the Building Inspector.
How long is a Ramapo building permit valid?
Two years from the date of issuance under § 376-146A. If construction started but is incomplete, the Building Inspector can grant a one-year extension for half the original fee, then a second one-year extension for a quarter of the fee.
What happens if I build without a permit in Ramapo?
Section 376-1413 makes it punishable by a fine up to $5,000, up to 15 days in jail, or both, with each day of continued violation treated as a separate offense. The Town can also pursue other remedies available under state or local law.

Sources & Official References

Other rules in Ramapo

All Ramapo rules

New York rules heatmap·Compare Ramapo to another location·View the New York building safety overview

Get notified when Building Permits in Ramapo, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.