Key Facts
- Permit validity
- 24 months from issuance (§123-11A)
- Extensions
- Up to four 6-month extensions for good cause
- Unpermitted work
- Fee doubled under §123-12C
- Historic (pre-1941) referral
- 45-day Landmarks Board review
- Storage sheds
- No permit, but owner certification required
- Max penalty
- $1,000 per day, unclassified misdemeanor
Summary
In the Town of Southampton outside the villages, a building permit from the Building Inspector is required before erecting, altering, enlarging or changing the use of any building or structure, separate from any Zoning Ordinance permit. Only ordinary, nonstructural repairs and specific Town Board-listed work are exempt under §§ 123-8 and 123-9.
§ 123-8. Work not requiring building permit or demolition permit. ... An application for a building permit or a demolition permit is not required where there is no change in the perimeter or structural elements of an existing structure which is being repaired, improved or remodeled, or for such kinds, types and methods of repairs, improvements and alterations as the Town Board shall specify from time to time in regulations adopted by said Board by resolution applicable to this article. ... ... § 123-9. Application for building or demolition permit. ... A. Building permit required. (1) No person, firm or corporation shall commence the erection, construction, enlargement, alteration, improvement, conversion or change in the use or nature of the occupancy of any building or structure or cause the same to be done without first obtaining a building permit, separate and distinct from that required by the Zoning Ordinance, from the Building Inspector for each such building or structure; except that no building permit shall be required for the performance of ordinary repairs which are not structural in nature, except as provided herein.
Full Breakdown
Southampton Town Code § 123-9A(1) makes it unlawful to commence erection, construction, enlargement, alteration, improvement, conversion or a change in use or occupancy of any building or structure without first obtaining a building permit from the Building Inspector, distinct from any Zoning Ordinance permit, with a narrow carve-out for ordinary repairs that are not structural in nature. Section 123-8 exempts work that changes no perimeter or structural element of an existing structure and that the Town Board has specifically listed by resolution, though even an exempt residential storage shed still needs an owner's certification of zoning compliance.
A permit application touching a building built before 1941, identified from the Assessor's actual-year-built record or a listed heritage survey, is automatically referred to the Landmarks and Historic Districts Board, which has 45 days to report or recommend under § 123-9A(1)(a). Separate applications are required for electrical work (filed with the Building Division under § 123-9A(3)) and for plumbing or drainage systems (§ 123-9A(4)), and a permit is independently required for any regulated wetlands activity under Chapter 325. Once issued, a permit stays effective for 24 months under § 123-11A, with up to four extensions of six months each available for good cause; after that a new application and fee are required. Fees are set by Town Board resolution, and § 123-12C doubles every fee tied to work found underway without the required permit.
Violations & Fines
Constructing, altering or occupying a building without the required permit, or in a manner not authorized by the permit issued, is unlawful under § 123-21B: an unclassified misdemeanor punishable by a fine of up to $1,000 per day per offense or imprisonment up to one year, plus a mandatory $100 blight mitigation surcharge. Work caught underway without a permit also triggers a doubled fee under § 123-12C, and defying a resulting stop-work order adds a $750-to-$1,000-per-day fine.
Frequently Asked Questions
Does every home project in Southampton need a building permit?
How long is a Southampton building permit good for?
What happens if I start construction without a permit?
Do older houses face extra permit steps in Southampton?
Sources & Official References
Other rules in Southampton
New York rules heatmap·Compare Southampton to another location·View the New York building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Suffolk County handle building permits.