Key Facts

Permit lead time
8 hrs before work (24 hrs emergency)
Exempt repairs
single-family, $1,000 or less
Application review
up to 60 calendar days
Unpermitted penalty
100% of permit fee
Application abandoned
180 days without permit
Permit voids
180 days unstarted or uninspected

Summary

The City of Stonecrest requires a permit before any construction, erection, alteration or repair to a building, structure, or its mechanical, gas, plumbing or electrical systems under Sec. 7-118(a). Only ordinary repairs to a single-family home costing $1,000 or less skip the process; everyone else must apply through the Community Development Department's Building Official first.

(a)Permit required. A permit shall be obtained before beginning construction, erection, alteration or repair to a building or structure, mechanical system, gas system, plumbing system, electrical system, and energy conservation system, other than ordinary repairs. Permits shall be obtained at least eight hours before beginning work. Permits for emergency work shall be obtained within 24 hours after work is commenced.(b)Exception to permit required. Ordinary repairs to a single-family residential building or structure for which the wholesale cost does not exceed $1,000.00 shall not be required to obtain a permit.(c)Work commencing before permit issuance. In addition to any other remedies provided by law, any person, contractor or company commencing any work on a building or structure, mechanical, gas, plumbing, or electrical system before obtaining the required permit shall be subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fee as well as a Stop Work Order.

Full Breakdown

Sec. 7-118(a) states plainly that a permit shall be obtained before beginning construction, erection, alteration or repair to a building or structure, mechanical system, gas system, plumbing system, electrical system, and energy conservation system, other than ordinary repairs, and requires the permit at least eight hours before work starts, or within 24 hours for emergency work. Sec. 7-118(b) exempts only ordinary repairs to a single-family residential building whose wholesale cost is $1,000 or less. The application itself, described in Sec. 7-118(e), must identify the work, describe the property by street address or legal description, state the intended use, include construction plans and the proposed valuation, and carry the signatures of both the applicant/contractor and the property owner.

The Building Official must examine a complete application within 60 calendar days under Sec. 7-118(f), and may issue a special foundation-only permit while the rest of the application is pending. An application is deemed abandoned 180 days after filing unless a permit issues, though the Building Official may grant up to three 90-day written extensions for justifiable cause under Sec. 7-118(g). Once issued, a permit becomes invalid if work does not begin within 180 days, if no city inspection occurs within a year, or if work is suspended for 180 days, per Sec.

7-118(i). Sec. 7-118(c) penalizes anyone who starts work before the permit issues: 100 percent of the usual permit fee on top of the fee itself, plus a Stop Work Order. Permit fees themselves are set by the city council and kept on file with the city clerk under Sec. 7-120(b).

Violations & Fines

Beginning construction, alteration or repair without first obtaining the Sec. 7-118(a) permit exposes the property owner or contractor to a penalty equal to 100 percent of the standard permit fee, billed in addition to the required fee, along with an immediate Stop Work Order. Continued defiance of a stop order is prosecuted in municipal court under Sec. 7-62(c), with each day of continued work treated as a separate offense.

Frequently Asked Questions

What triggers the building permit requirement in Stonecrest?
Sec. 7-118(a) requires a permit before any construction, erection, alteration or repair to a building or structure, or to its mechanical, gas, plumbing or electrical systems, except ordinary repairs. The application goes through the Community Development Department's Building Official before work can start.
Is there a small-repair exemption from Stonecrest's permit rule?
Yes. Sec. 7-118(b) exempts ordinary repairs to a single-family residential building or structure when the wholesale cost of the repair does not exceed $1,000.00, so minor fixes below that threshold do not need a permit application.
What happens if work starts before a Stonecrest building permit is issued?
Sec. 7-118(c) imposes a penalty equal to 100 percent of the usual permit fee, added to the fee itself, and the Building Official can issue a Stop Work Order that immediately halts the job until the permit is obtained.

Sources & Official References

Other rules in Stonecrest

All Stonecrest rules

Compare Stonecrest to another location·View the Georgia building safety overview

Get notified when Building Permits in Stonecrest, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.