Beaumont, CA Building Safety: Electrical Permits (2026)
Key Facts
- Code adopted
- 2025 California Electrical Code, Title 24, Part 3
- Fee rules
- Follow items 109.1 to 109.6 of § 15.04.020
- Application limit
- 12 months, extensions up to 180 days each
- Power connection
- Needs building inspector's certificate of approval
- Unpermitted work
- Investigation fee equal to the permit fee
- Penalty
- Infraction
Summary
In the City of Beaumont, California, the 2025 California Electrical Code (Title 24, Part 3) is adopted as the City Electrical Code, and local amendments tie electrical permit fees and expiration to Chapter 15.04. Connecting power to a permitted installation without the building inspector's certificate of approval is an infraction.
Except as otherwise provided in this Chapter, the California Electrical Code, Title 24, California Code of Regulations, Part 3, including any and all amendments set forth in this chapter, and including any and all amendments thereto that may hereafter be made and adopted by the State of California, is hereby adopted by reference as the City Electrical Code except as modified by this Chapter. ... 89.108.4.3.2 Permit Expiration. Shall be pursuant to Beaumont Municipal Code Chapter 15.04; Section 15.04.020; Item 105.5 Expiration and 105.5.1 Work Commenced Without Permit. ... B.It shall be a violation of this Chapter, punishable as an infraction, for any person, firm or corporation to make connection from a source of electrical energy to an installation for which a permit is required, unless such person, firm or corporation has obtained a certificate of approval from the building inspector that such wiring devices. Appliances or equipment are in conformity with all the requirements of this code.
Full Breakdown
Section 15.12.010 of the Beaumont Municipal Code adopts the California Electrical Code, Title 24, Part 3, as the City Electrical Code in the City of Beaumont, California. The adoption picks up later state amendments automatically. Section 15.12.020 then amends the 2025 edition, and every local amendment points back to the building code chapter rather than writing separate electrical rules.
Payment of fees follows item 109.1 of § 15.04.020, so plan check fees and deposits, permit fees, re-inspection fees, special inspection fees and investigation fees are collected before a permit issues, in amounts set by City Council action. The schedule of permit fees follows item 109.2 and the city fee schedule. Plan review and the time limit on an application follow item 105.3.2, under which an application with no permit issued within 12 months expires and extensions run up to 180 days each. Permit expiration follows items 105.5 and 105.5.1: a permit is invalid if work does not start within 12 months or is suspended for 365 days, and work started without a permit must pass its first inspection within 30 calendar days of issuance.
Work commencing before permit issuance follows item 109.4, so a special investigation is made first and its cost equals the permit fee. Related fees follow item 109.5, including re-inspection fees when corrections are not made. Refunds follow item 109.6, which lets the building official refund up to 80 percent of a permit fee when no work has been done, on written application within 180 days of payment.
Section 15.12.030 B adds a connection rule. No person, firm or corporation can connect a source of electrical energy to an installation that requires a permit until the building inspector has issued a certificate of approval showing the wiring devices, appliances or equipment conform to the code.
Violations & Fines
Under § 15.12.030, violating Chapter 15.12 or failing to meet any requirement of the Electrical Code is an infraction. Making an electrical connection to a permitted installation without the certificate of approval from the building inspector is a separate violation, also punishable as an infraction. Starting electrical work before a permit issues also draws the investigation fee equal to the permit fee under item 109.4 of § 15.04.020.
Frequently Asked Questions
Which electrical code does Beaumont use?
Can power be connected before the Beaumont building inspector signs off?
How long does an electrical permit last in Beaumont?
What if electrical work in Beaumont started before the permit?
Sources & Official References
Other rules in Beaumont
California rules heatmap·Compare Beaumont to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in Riverside County handle electrical permits.