Key Facts

Code adopted
2025 California Plumbing Code, Title 24, Part 5
Fee payment
Follows item 109.1 of § 15.04.020
Expiration
Follows items 105.5 and 105.5.1
Work before permit
Investigation fee equal to the permit fee
Refunds
Up to 80 percent of permit fee if no work done
Penalty
Infraction

Summary

In the City of Beaumont, California, the 2025 California Plumbing Code (Title 24, Part 5) is adopted as the city's Plumbing Code. Local amendments send plumbing permit expiration, fees and work started before a permit to the building code's items 105.5, 109.1 and 109.4. A violation is an infraction.

Except as otherwise provided in this Chapter, the California Plumbing Code, Title 24, California Code of Regulations, Part 5, including any and all amendments set forth in this chapter, and including any and all amendments thereto that may hereafter be made and adopted by the State of California, is hereby adopted by reference as the Plumbing Code of the City except as modified by this Chapter. ... 104.4.3 Expiration Shall be pursuant to Beaumont Municipal Code Chapter 15.04; Section 15.04.020; Item 105.5 Expiration 105.5.1 Work Commenced Without Permit ... 104.5. ... 2 Work commencing before permit issuance. Shall be pursuant to Beaumont Municipal Code Chapter 15.04; Section 15.04.020; Item 109.4 Work commencing before permit issuance.

Full Breakdown

Section 15.16.010 of the Beaumont Municipal Code adopts the California Plumbing Code, Title 24, California Code of Regulations, Part 5, as the Plumbing Code of the City of Beaumont, California, including later state amendments, except as modified by the chapter. Section 15.16.020 amends the 2025 edition and titles it the Plumbing Code of the City of Beaumont. The amendments do not write separate plumbing permit rules. Each one points to a specific item in § 15.04.020.

The time limit on an application (item 104.3.3) follows item 105.3.2: an application with no permit issued within 12 months of filing expires, with extensions of up to 180 days each. Expiration of a plumbing permit (item 104.4.3) follows items 105.5 and 105.5.1: the permit is invalid if work does not start within 12 months or is suspended or abandoned for 365 days, and work begun without a permit must pass its first inspection within 30 calendar days of the permit's issuance.

Payment of fees (item 104.5) follows item 109.1, covering plan check fees and deposits, permit fees, re-inspection fees, special inspection fees and investigation fees, all set by City Council action. The schedule of permit fees (item 104.5.1) follows item 109.2 and the city fee schedule. Work commencing before permit issuance (item 104.5.2) follows item 109.4, which requires a special investigation before a permit issues at a cost equal to the permit fee. Related fees (item 104.5.3) follow item 109.5, and refunds (item 104.5.4) follow item 109.6, under which the building official can refund up to 80 percent of a permit fee if no work was done, on written application within 180 days of payment.

Violations & Fines

Under § 15.16.030, violating Chapter 15.16 or failing to comply with any requirement of the Plumbing Code is an infraction. Starting plumbing work before a permit issues triggers the special investigation fee equal to the permit fee under item 109.4, charged in addition to the permit fee, and the accelerated inspection schedule in item 105.5.1. Re-inspection fees can be assessed when corrections are not made.

Frequently Asked Questions

Which plumbing code applies in Beaumont?
Section 15.16.010 adopts the California Plumbing Code, Title 24, Part 5, as the Plumbing Code of the City of Beaumont, with later state amendments included. The 2025 edition is amended by § 15.16.020, which retitles it and points the permit and fee provisions to the building code chapter.
When does a Beaumont plumbing permit expire?
Item 104.4.3 follows items 105.5 and 105.5.1 of § 15.04.020. A permit is invalid if work does not start within 12 months of issuance, or if work is suspended or abandoned for 365 days. Written extensions of up to 180 days each are available from the building official with justifiable cause and a fee.
What happens if plumbing work starts before the permit in Beaumont?
Item 104.5.2 sends the situation to item 109.4, which requires a special investigation before the permit can issue. The investigation costs the same as the permit fee and is collected in addition to it. Item 105.5.1 then sets a 30-calendar-day deadline for the first inspection after the permit issues.
Can I get a refund on a Beaumont plumbing permit?
Item 104.5.4 follows item 109.6. The building official can refund up to 80 percent of the permit fee when no work has been done under the permit, but only on a written application from the original permittee filed within 180 days after the fee was paid. Erroneously paid fees can also be refunded.

Sources & Official References

Other rules in Beaumont

All Beaumont rules

California rules heatmap·Compare Beaumont to another location·View the California building safety overview

Get notified when Plumbing Permits in Beaumont, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Nearby Cities

How other cities in Riverside County handle plumbing permits.

Riverside, CA
Some Restrictions
Palm Springs, CA
Some Restrictions
Corona, CA
Some Restrictions
Menifee, CA
Some Restrictions
Murrieta, CA
Some Restrictions
Moreno Valley, CA
Some Restrictions
Temecula, CA
Some Restrictions