Chicago, IL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Enforcing agency
Chicago Department of Buildings
Footing/foundation inspection
After excavation, rebar placed
Framing inspection
After roof deck, rough MEP done
Final inspection
After work substantially complete
Concealing uninspected work
Prohibited until sign-off

Summary

Chicago requires permit holders to request footing, framing, and final inspections at set construction stages, and bars covering completed work until the building official signs off.

The permit holder must notify the building official when work done pursuant to a permit is ready for the types of inspections listed in Sections 14A-5-502.3.1 through 14A-5-502.3.5... Footing and foundation inspections must be requested after excavations for footings are complete and any required reinforcing steel is in place... Framing inspections must be requested after the roof deck or sheathing, framing, fire-blocking, and bracing are in place... The final inspection must be requested after all work required by the building permit is substantially completed.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-74: Current through Council Journal of June 17, 2026).

Full Breakdown

Chicago's Department of Buildings runs permitted construction inspections in stages, not one pass. The permit holder must notify the building official when work reaches each stage: footing and foundation inspection once excavation is done and rebar is placed, concrete slab/under-floor inspection before pouring, framing inspection after the roof deck, framing, fire-blocking and rough electrical/plumbing/heating are in and inspected, and a final inspection once all permitted work is substantially complete. Electrical, plumbing, mechanical and ventilation trades each get their own rough and final inspections. Inspected work can't be covered or concealed until the building official signs off.

Violations & Fines

Concealing inspected work without sign-off, or building beyond permit scope, can trigger a stop-work order and a penalty of 100%-200% of the regular permit fee under § 14A-12-1204.4.

Frequently Asked Questions

Who has to request building inspections in Chicago?
The permit holder or their authorized agent must notify the building official when work is ready for each required inspection stage, per MCC § 14A-5-502.1.
What happens if I cover work before it's inspected?
You may not conceal an inspected condition until the building official authorizes it; doing so can bring a stop-work order and a penalty of up to 200% of the permit fee.

Sources & Official References

Other rules in Chicago

All Chicago rules

Compare Chicago to another location·View the Illinois building safety overview

Get notified when Building Inspections in Chicago, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Cook County handle building inspections.

Evanston, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Tinley Park, IL
Some Restrictions
Skokie, IL
Some Restrictions
Schaumburg, IL
Some Restrictions