Key Facts

Trigger
Incomplete work or uncorrected prior deficiency at inspection
Fee source
Set by City Council Fee Resolution
Access failure
Also charged for no site access, missing plans/card
Consequence
No further inspections until fee is paid
Governing section
CBC § 110.7, San Clemente Municipal Code § 15.08.020

Summary

San Clemente's Building Division charges a re-inspection fee whenever a scheduled inspection finds the work incomplete, prior corrections unfixed, or the site inaccessible, under amended CBC Section 110.7 (Municipal Code Section 15.08.020). No further inspections happen until the fee, set by City Council resolution, is paid.

110.7 Re-inspections. A re-inspection fee may be assessed for each inspection or re-inspection when such portion of work for which an inspection is requested is not complete or when previous corrections are not corrected. This subsection is not to be interpreted as requiring re-inspection fees the first time a job is rejected for failure to comply with requirements of this Code, but as controlling the practice of calling for inspections before the job is ready for such inspection or re-inspection. Re-inspection fees may be assessed when the inspection record card is not posted or otherwise made available on the work site, or when the approved plans are not readily available to the inspector, or for failure to provide access on the date for which inspection is requested. To obtain a re-inspection, the applicant shall pay the re-inspection fee as established by the City Council Fee Resolution. In instances where re-inspection fees have been assessed, no additional inspection of work will be performed until the required re-inspection fees have been paid.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Traffic: Supplement 30 | Code of Ordinances: Supplement 66 Update 1).

Full Breakdown

When the City adopted the 2025 California Building Code on November 4, 2025 (Ordinance No. 1796), it added a new Subsection 110.7, Re-inspections, to Chapter 1's administrative provisions. The rule lets the Building Official assess a re-inspection fee any time a contractor or owner calls for an inspection but the relevant portion of the work is not actually finished, or a previously flagged correction still has not been made. It is not meant to punish a project's first failed inspection: the code specifically says the fee is not for the first time a job is rejected for noncompliance, but exists to stop the practice of calling for inspections before work is genuinely ready.

Beyond incomplete work, the fee can also be triggered by paperwork and access problems: the inspection record card is not posted or available on site, the approved plans are not on hand for the inspector to check against, or nobody provides access to the property on the date the inspection was requested. Once a re-inspection fee is assessed, the applicant has to pay the amount set in the City Council's Fee Resolution before scheduling the next visit, and the code is explicit that the City will perform no additional inspection of the work until that fee is paid. This sits alongside a separate, older enforcement tool at Section 15.04.050, which lets a Code Enforcement Officer issue a correction notice with its own 30-day grace period and reinspection fee for property found out of compliance with the Building, Electrical, Plumbing, Mechanical or wildfire fuel-modification chapters, backed by the City's delinquent-accounts-receivable collection process for unpaid invoices.

Violations & Fines

An unpaid re-inspection fee stalls the project: the City will not send an inspector back out, and will not sign off on any further work, until it is paid. Under the related Section 15.04.050 process for existing-property violations, a Code Enforcement Officer can also issue successive correction notices and additional reinspection fees, and unpaid invoices go to the City's delinquent-accounts collection procedure.

Frequently Asked Questions

When does San Clemente charge a building re-inspection fee?
Whenever an inspector shows up and the portion of work called for is not actually complete, or a correction flagged at an earlier inspection still has not been fixed, under CBC Section 110.7 as adopted in Municipal Code Section 15.08.020. It also applies if the inspection record card, approved plans, or site access are not available for the inspector.
Do I get charged a fee the first time an inspection fails?
No. Section 110.7 specifically says the fee is not meant for the first time a job is rejected for noncompliance; it targets the practice of repeatedly calling for inspections before the work is genuinely ready, or failing to fix flagged corrections before the next visit.
What happens if I do not pay the re-inspection fee?
The Building Division will not perform any additional inspection of your work until the fee, set under the City Council's Fee Resolution, is paid. That effectively halts your project's progress since most permits require passing inspections at each stage before work can continue.

Sources & Official References

Other rules in San Clemente

All San Clemente rules

California rules heatmap·Compare San Clemente to another location·View the California building safety overview

Get notified when Building Inspections in San Clemente, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Orange County handle building inspections.

Santa Ana, CA
Some Restrictions
Fullerton, CA
Some Restrictions
Newport Beach, CA
Some Restrictions
Costa Mesa, CA
Some Restrictions