Skip to main content
CityRuleLookup

Ogden, UT Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Code adopted
International Plumbing Code, section 16-2-2
Unpermitted work fee
Up to 100% of the permit fee
Sewer connection
Required within 300 feet of a sewer line
Appeal filing fee
$100.00 to board of appeals
Enforcing division
Building Services, Community and Economic Development

Summary

Ogden City Code section 16-2-2 folds the International Plumbing Code into the state construction code that applies to every building in the city. Starting plumbing work before pulling the required permit exposes a contractor or owner to an enhanced fee of up to 100% of the normal permit cost under section 16-1-4.

16-1-4: FEES ADOPTED: ... C. At the discretion of the building official, a person who commences any work on a building, structure, electrical, gas, mechanical or plumbing system before obtaining the necessary permits shall be subject to an enhanced fee in an amount up to one hundred percent (100%) of the total permit fee that would have been assessed under the base fee schedule for the work which was performed before the required permit was issued. ... 16-2-2: ... CODES ADOPTED: ... A. The State Construction Code, as defined in section 15A-1-204, Utah Code Annotated, as amended or superseded, and the State Fire Code, as defined in section 15A-1-403, Utah Code Annotated, as amended or superseded, are hereby adopted as the rules, regulations and standards for the construction, occupancy, alteration, remodeling and repair of all structures and buildings in the City. The State Construction and Fire Code includes: ... 7. The International Plumbing Code (IPC);

Full Breakdown

Ogden City Code section 16-2-2 adopts the state construction code, defined by Utah Code Annotated section 15A-1-204, as the governing standard for construction, occupancy, alteration, remodeling and repair citywide, and names the International Plumbing Code as one of the specific model codes carried within that state code alongside the National Electric Code, International Mechanical Code and International Fuel Gas Code. Any water supply, drain, waste, vent or fixture work covered by the IPC needs a plumbing permit from Ogden's Building Services Division before work starts, with inspection required under the technical codes adopted by chapter 2.

Section 16-1-4 attaches a real cost to skipping that step: work started before a permit issues can draw an enhanced fee of up to one hundred percent of the total permit fee that would have been charged under the base fee schedule, in addition to the ordinary permit and plan review fees. Ogden also ties plumbing directly to sewer connection rules; section 9-3-3 requires any septic tank disposal system to be installed in accordance with the plumbing code adopted under title 16, and section 9-3-2 requires toilet facilities within three hundred feet of a sewer line to connect to the city sewer system rather than rely on a septic system.

A disputed permit or fee decision goes to the board of building and fire code appeals for a one hundred dollar filing fee under section 16-1-7.

Violations & Fines

Plumbing work done before a permit issues brings the enhanced fee in section 16-1-4, up to double the normal permit cost, plus the standard permit and plan review fees once the permit is finally obtained. Unpermitted work that also fails IPC standards can bring a stop-work order, and section 16-1-5 applies chapter 12's penalties, including civil citations, for continued technical code violations.

Frequently Asked Questions

Do I need a permit for plumbing work in Ogden?
Yes. Ogden City Code section 16-2-2 adopts the International Plumbing Code as part of the city's technical codes, so water supply, drain and fixture work covered by the IPC needs a permit and inspection from the Building Services Division before it's complete.
What's the penalty for plumbing work without a permit in Ogden?
Section 16-1-4 allows the building official to charge an enhanced fee up to 100 percent of the normal permit fee for plumbing work started before the permit was obtained. That's in addition to the standard permit and plan review fees.
Can I keep a septic tank instead of connecting to Ogden's sewer?
Only if no part of the property is within three hundred feet of a sanitary sewer system. Section 9-3-2 requires sewer connection within that distance, and any septic system that is allowed must meet the plumbing code standards under section 9-3-3.

Sources & Official References

Other rules in Ogden

All Ogden rules

Compare Ogden to another location·View the Utah building safety overview

Get notified when Plumbing Permits in Ogden, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.