Bossier City, LA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Threshold
1 acre or more of disturbed land
Enforcing agency
Director of public utilities
Inspection interval
Every 7-14 days, per BMP schedule
First-offense fine
$500.00 per day per offense
Legal citation
Bossier City Code Ch. 114, Art. IV

Summary

Bossier City requires erosion and sediment control best management practices on any construction site disturbing one acre or more of land. The director of public utilities administers the program, and violators face director-imposed fines starting at $500.00 per day.

Any construction activity located within the city that includes ground clearing, land grading, excavation, and other land disturbing activities, resulting in the disturbance of one acre or more of total land area, is subject to the requirements of this ordinance. ... Any operator and/or owner of a construction site shall use erosion and sediment BMP's to control and reduce the discharge of pollutants to the MS4 and to waters of the state. Sediment, silt, soil and other materials associated with clearing, grading, excavation and other construction activities shall be retained on site or captured by employing BMP's to the maximum extent practicable under prevailing circumstances. ... An operator and/or owner who willfully or negligently violates any provision of this article, or any other related laws or regulations shall be punished by a fine imposed by the director according to the following schedule of offences:(1)First offence: $500.00 per day per offence.(2)Second offence: $1,000.00 per day per offence.(3)Third offence: $1,500.00 per day per offence.

Full Breakdown

Under Article IV of Chapter 114, any construction activity in Bossier City that includes ground clearing, land grading, excavation or other land-disturbing work on one acre or more of total land area triggers the city's erosion and sediment control ordinance, including projects that are part of a larger common plan that will ultimately disturb an acre or more. Operators and owners must retain sediment, silt and soil on-site to the maximum extent practicable using best management practices (BMPs) covering waste control, ready-mix concrete washout areas, spill housekeeping and construction-entrance sediment tracking.

BMPs implemented at a site must be inspected at least once every seven days, or every 14 days between anticipated storm events, and within 24 hours after a storm of 0.5 inches or more. The director of public utilities administers the ordinance and may issue a written notice of violation (NOV); failure to comply becomes a separate violation for each day beyond the 30th day following the NOV, and the director can order work stopped immediately without first issuing an NOV. An operator or owner who willfully or negligently violates the article is fined on an escalating per-day, per-offense schedule set by the director, and the city may also bill the violator for its actual surveillance, sampling, abatement and remediation costs.

Violations & Fines

First offense costs $500.00 per day per offense, rising to $1,000.00 per day for a second offense and $1,500.00 per day for a third, all assessed by the director of public utilities. The city can also stop work immediately by posted written notice and recover its cleanup, inspection and remediation costs from the responsible operator or owner.

Frequently Asked Questions

What triggers Bossier City's erosion control ordinance?
Any construction activity, including clearing, grading, excavating or demolition, that disturbs one acre or more of land within the city triggers the ordinance, as does a smaller phase of a larger common development plan that will eventually disturb an acre or more.
Who enforces erosion and sediment control on job sites?
The director of public utilities administers Chapter 114, Article IV, with authority to inspect sites, issue notices of violation, order work stopped, and assess escalating daily fines against the operator or owner responsible for a site.
How often must a builder inspect erosion controls?
Operators and owners must inspect their BMPs at least once every seven days, or at least every 14 calendar days between anticipated storms, and again within 24 hours after any storm event of 0.5 inches or greater.

Sources & Official References

Other rules in Bossier City

All Bossier City rules

Compare Bossier City to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in Bossier City, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.