Casa Grande, AZ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing chapter
Casa Grande Municipal Code Ch. 18.12
Permit trigger
1+ acre disturbed, or common-plan parcel under 1 acre
Permit review time
30 days for Public Works Director decision
Stabilization deadline
5 days after clearing or inactivity
Maximum penalty
$2,500 fine per offense, per day
Adopted by
Ord. 1397.18, § 1, 2019

Summary

In the City of Casa Grande, any land-disturbing activity uncovering one acre or more, or a smaller parcel that is part of a common plan of development, needs a site development permit and an approved SWPPP with specific erosion and sediment control measures under Chapter 18.12.

18.12.020 Permits. ... A. No person shall be granted a site development permit for land-disturbing activity that would require the uncovering of one or more acres of land, or which will disturb less than one acre that is part of a common plan of development, without the approval of a SWPPP by the city. ... 18.12.050 Design requirements. ... D. Erosion control requirements shall include the following: 1. Soil stabilization shall be completed within five days of clearing or inactivity in construction; ... 18.12.070 Enforcement. ... B. Violation and Penalties. ... Any person violating any of the provisions of this chapter shall be deemed guilty of a Class 1 misdemeanor, and each day during which any violation of any of the provisions of this chapter is committed, continued or permitted, shall constitute a separate offense. Upon conviction of any violation, the person, partnership or corporation shall be punished by a fine of not more than two thousand five hundred dollars for each offense, per day.

Full Breakdown

Casa Grande Municipal Code Chapter 18.12, Construction Stormwater Management, requires a site development permit before land-disturbing activity uncovering one or more acres, or disturbing less than one acre as part of a common plan of development, proceeds without an approved Stormwater Pollution Prevention Plan (SWPPP) (§ 18.12.020(A)). Applications must name the owner, developer, and any consulting firm, and include a filing fee (§ 18.12.020(B)); the Public Works Director has thirty days to approve, conditionally approve, or disapprove the application (§ 18.12.030). The erosion and sediment control plan required under § 18.12.040 must sequence construction activity (stripping, rough grading, utility work, final grading and landscaping) and identify the erosion and sediment control measures used throughout each phase.

Design requirements under § 18.12.050 tie grading and sediment control practices to the MCFCD Drainage Policies and Standards and require phasing on any site disturbing more than thirty acres. Specific erosion control measures include completing soil stabilization within five days of clearing or inactivity, establishing vegetative cover within two weeks or reseeding, stabilizing soil stockpiles at the end of each workday, and preventing sediment or dust from leaving the site (§ 18.12.050(D)). Sediment controls must include settling basins, sediment traps, or perimeter controls, plus vegetated buffer strips protecting adjacent properties (§ 18.12.050(E)).

The Public Works Director inspects at the start of construction, at installation of control measures, at final grading, at the close of the construction season, and at final landscaping, with two working days' notice required (§ 18.12.060).

Violations & Fines

A permit holder who violates permit terms or endangers neighborhood health, welfare or safety can have the site development permit suspended or revoked under § 18.12.070(A). Under § 18.12.070(B), violating any provision of Chapter 18.12 is a Class 1 misdemeanor, with each day of a continuing violation a separate offense, punishable by a fine of up to $2,500 per offense per day; a convicted violator must also bear the cost of restoring the site.

Frequently Asked Questions

When does a construction project in Casa Grande need an erosion control permit?
A site development permit and approved SWPPP are required for land-disturbing activity uncovering one acre or more, or for a smaller parcel that is part of a common plan of development, under § 18.12.020(A).
How fast must exposed soil be stabilized on a Casa Grande construction site?
Section 18.12.050(D) requires soil stabilization within five days of clearing or of inactivity in construction, and any seeded areas must establish within two weeks or be reseeded at the Public Works Director's direction.
What inspections does the city require during grading work?
The permittee must give the Public Works Director two working days' notice before the start of construction, installation of erosion controls, completion of final grading, the close of the construction season, and completion of final landscaping, per § 18.12.060.
What is the penalty for violating Casa Grande's construction stormwater rules?
Under § 18.12.070(B), a violation is a Class 1 misdemeanor punishable by a fine of up to $2,500 per offense per day, with the violator also required to bear the cost of restoring the disturbed site.

Sources & Official References

Other rules in Casa Grande

All Casa Grande rules

Compare Casa Grande to another location·View the Arizona environmental rules overview

Get notified when Erosion Control in Casa Grande, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.