Grand Junction, CO Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger threshold
1+ acre of disturbed soil or vegetation removal
Plan required
Construction storm water management plan
Plan approval by
Community Development Department
BMP inspection frequency
At least every 14 days, plus storm events
Tracked sediment
Removed immediately, owner's expense
Modification deadline
7 calendar days after inspection

Summary

In the City of Grand Junction, construction disturbing one acre or more of soil must follow a City-approved construction storm water management plan with erosion and sediment control BMPs before work starts, and any sediment tracked onto public streets must be removed immediately at the owner's expense.

§ 13.28.030. Control of storm water discharges from construction and post-construction activities. (a) General Requirements for Construction Sites. (1) All proposed development as described in subsection (a)(2) of this section must provide for on-site erosion and sediment control, control of illegal discharges, and runoff collection and conveyance in accordance with the Stormwater Management Manual and applicable federal and State laws. ... (5) Erosion and Sediment Control. BMPs shall be implemented to prevent the release of sediment from construction sites and development. Disturbed area(s) shall be minimized and disturbed soil, including but not limited to construction sites and entrances and exits therefrom, shall be managed to prevent tracking, blowing and fugitive emissions release. Any water used in cleaning operations shall not be disposed into the storm sewer system. Sediment, dirt and mud tracked onto public streets shall be removed immediately by sweeping, scooping and shoveling at the owner’s expense.

Full Breakdown

Grand Junction Municipal Code § 13.28.030(a) requires all covered development to provide on-site erosion and sediment control, illegal-discharge control, and runoff collection consistent with the City's Stormwater Management Manual. Under (a)(2), any owner whose project disrupts or exposes soil or removes vegetation on one acre or more during the life of the project must obtain a State discharge permit and use specific best management practices (BMPs) adopted by the City. Subsection (a)(5), Erosion and Sediment Control, requires BMPs to prevent sediment release, minimizes disturbed areas, and requires disturbed soil, including at site entrances and exits, to be managed to prevent tracking, blowing and fugitive emissions; sediment, dirt or mud tracked onto public streets must be removed immediately by sweeping, scooping or shoveling at the owner's expense, and if not removed within the time stated in a City notice, the City or its contractor removes it and bills the property owner, with unpaid costs becoming a property lien.

Section 13.28.030(b) requires a written construction storm water management plan, reviewed and approved by the Community Development Department before construction starts, for any project (including phased common plans of development) disturbing one acre or more; the plan must be prepared under a qualified person per (c), and under (d) the owner must inspect all BMPs at least once every 14 days and after any precipitation or snowmelt event causing erosion, correcting major modifications within seven calendar days of an inspection showing they are needed. Post-construction, permanent BMPs must be maintained in good working condition for the life of the development under (e), and a qualified person must certify compliance before a certificate of occupancy issues under (f).

Violations & Fines

Enforcement runs through § 13.28.040: the City Manager may issue stop-work orders posted at the site barring further construction or occupancy inspections, order abatement with costs billed to the owner and liened if unpaid, and refer violations for criminal prosecution as a municipal offense under § 13.28.040(m), punishable by fine or imprisonment under § 1.04.090, with each day of noncompliance a separate offense. Failure to remove tracked sediment within the City's notice period lets the City perform the cleanup and bill the property owner directly under § 13.28.030(a)(5).

Frequently Asked Questions

When does a Grand Junction construction site need an erosion control plan?
Under § 13.28.030(b), any project, including phased developments that are part of a larger common plan, that disturbs or exposes soil or removes vegetation on one acre or more needs a construction storm water management plan approved by the Community Development Department before construction begins.
Who pays if mud tracks onto the street from a job site?
The property owner. Section 13.28.030(a)(5) requires immediate removal of sediment, dirt or mud tracked onto public streets at the owner's expense; if it is not cleared within the City's stated time frame, the City removes it and bills the owner, with unpaid costs becoming a lien.
How often must BMPs be inspected during construction?
Section 13.28.030(d)(3) requires the owner to inspect all best management practices at least once every 14 days and after any precipitation or snowmelt event causing surface erosion, and to give the City standing consent to inspect BMPs without advance notice.

Sources & Official References

Other rules in Grand Junction

All Grand Junction rules

Compare Grand Junction to another location·View the Colorado environmental rules overview

Get notified when Erosion Control in Grand Junction, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.