Key Facts

Plan trigger (impervious area)
7,000+ sq ft impervious surface
Plan trigger (site size)
1 acre or more
Small-project exemption
5 units or fewer (still must comply)
Approving official
Dir., Inspections and Code Enforcement
Occupancy hold
No certificate of occupancy without compliance
Design goal
Non-erosive velocity of flow required

Summary

In the City of Kenner, any new development or redevelopment covering seven thousand square feet or more of impervious surface, or one acre or more of land, must submit a stormwater management plan under Section 10.04 of the Unified Development Code before a building permit issues, and Section 10.05's required Best Management Practices must keep runoff flowing at a non-erosive velocity.

(a)Stormwater Management Measures:(1)Effective on-site stormwater management is supported by a combination of stormwater BMPs ... guided by the following strategies:a.First, create conditions that allow detention and infiltration of stormwater runoff on-site through the use of pervious paving, open vegetated areas, green roofs, blue roofs, and other methods that allow water to permeate back into the ground. ... (2)Infiltration practices shall be utilized to reduce runoff volume increases, stabilize subsoils, and recharge shallow groundwater. ... (4)All stormwater management facilities shall be designed to provide an emergency overflow system, and incorporate measures to provide a non-erosive velocity of flow along its length and at any outfall.(5)The designed release rate of any stormwater structure shall be modified if any increase in flooding or stream channel erosion would result at a downstream dam, highway, structure, or normal point of restricted stream flow.

Full Breakdown

Kenner regulates construction-site erosion through its Stormwater Management article, Article X of the Unified Development Code, rather than a stand-alone erosion ordinance. Section 10.04(a) sets the applicability trigger: any new development or redevelopment disturbing seven thousand square feet or more of impervious surface, or covering one acre or more, must submit a stormwater management plan to the Director of the Department of Inspections and Code Enforcement, who approves it in consultation with a Louisiana-licensed landscape architect or civil engineer before a building permit is issued.

Single-family, two-family, and multifamily developments of five units or fewer are exempt from the plan requirement itself but must still comply with applicable federal, state, and local stormwater rules. Section 10.05(a) sets the technical erosion-control performance standards: on-site management must first rely on detention and infiltration through pervious paving, open vegetated areas, and green or blue roofs; additional runoff must be detained, stored, infiltrated, or filtered through Best Management Practices; infiltration practices must reduce runoff volume increases and stabilize subsoils; and every stormwater facility must be designed with an emergency overflow system and a non-erosive velocity of flow along its length and at any outfall, so that discharge does not cause downstream flooding or channel erosion.

Section 10.02 backs the whole article with a hard enforcement stop: no certificate of occupancy may issue for a covered lot until every stormwater requirement is met, and before occupancy a licensed engineer or landscape architect must certify by affidavit that the approved measures were actually installed.

Violations & Fines

Developing a covered site without an approved stormwater management plan, or building without the Best Management Practices shown on that plan, blocks issuance of a certificate of occupancy under Section 10.02 and exposes the project to the fines and penalties set out elsewhere in the Ordinance. Failing to maintain installed BMPs after occupancy, so the site no longer conforms to its approved plan, is separately cause for revoking the certificate of occupancy.

Frequently Asked Questions

Does Kenner have a separate erosion control permit for construction sites?
No freestanding erosion permit; erosion control is folded into the Stormwater Management article's plan-review process. Any project disturbing 7,000 square feet or more of impervious surface, or one acre or more, must get its stormwater management plan approved under Section 10.04 before a building permit issues.
What erosion-control design standard must my site plan meet?
Section 10.05(a) requires every stormwater facility to include an emergency overflow system and to be designed for a non-erosive velocity of flow along its length and at outfalls, plus infiltration practices that stabilize subsoils and reduce runoff volume increases.
Are small residential projects exempt from stormwater and erosion rules?
Single-family, two-family, and multifamily developments of five units or fewer do not need to submit a stormwater management plan, but Section 10.04(a) still requires them to comply with all other applicable federal, state, and local stormwater ordinances.
Can I get a certificate of occupancy before my BMPs are inspected?
No. Section 10.02 blocks a certificate of occupancy until every stormwater requirement is met, and a Louisiana-licensed engineer or landscape architect must certify by signed affidavit that the approved erosion-control measures were actually installed according to the approved plans and specifications.

Sources & Official References

Other rules in Kenner

All Kenner rules

Compare Kenner to another location·View the Louisiana environmental rules overview

Get notified when Erosion Control in Kenner, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.