Kenner, LA Environmental Rules: Stormwater Management (2026)
Key Facts
- Threshold
- 10,000 sq ft (non-residential) or 5 acres (residential)
- Design storm
- 10-year event; post can't exceed pre-development rate
- Extra check
- 100-year storm impact calculations required
- Design manual
- Jefferson Parish Storm Drainage Design Manual, 1981
- Enforcing agency
- City of Kenner Department of Public Works
- Prerequisite
- Permits withheld until director approves drainage plan
Summary
In the City of Kenner, developers building anything larger than 10,000 square feet, or five acres or more of single-family housing, must control stormwater runoff on-site under City Code § 13-53. The post-development rate of runoff during a ten-year storm can never exceed the pre-development rate, so most covered projects need an engineered detention design approved by the Department of Public Works before permits issue.
(a)For all proposed developments, other than single-family residential, totaling ten thousand (10,000) square feet or more of land area (all phases), and all single-family residential developments totaling five (5) acres or more (all phases), the ten-year storm event post-development rate of runoff shall not exceed the ten-year storm event predevelopment rate of runoff. To insure that the postdevelopment rate of runoff does not exceed the predevelopment of runoff, on-site detention will be required in a manner approved by the city department of public works. The detention system cannot release water from the site at a rate greater than the pre-development rate of runoff. ... (f)The City of Kenner director of the department of public works shall review for approval each proposed development covered by this section prior to the issuance of permits to proceed with said development.
Full Breakdown
City Code § 13-53 sets the drainage-detention standard for growth in the City of Kenner, a city built largely on drained wetlands where soil subsidence makes flood control non-negotiable. Any development other than single-family, totaling 10,000 square feet or more of land area counting all phases, and any single-family residential development of five acres or more, must hold the ten-year storm event post-development runoff rate at or below the pre-development rate. Compliance is achieved through on-site detention engineered so the release rate never exceeds the pre-development rate, using design concepts consistent with the Jefferson Parish 'Storm Drainage Design Manual' (1981 and later revisions) and the parish's 'Parking Lot Storm Runoff Detention Manual.' Before construction, the developer must submit drainage design calculations and a drainage map to the Department of Public Works, tracing the existing drainage system from the site outfall to the receiving outfall canal, plus calculations showing how the detention facility performs in a 100-year storm event.
Those calculations must cover drainage basin characteristics, system hydraulics, and any upstream or downstream influences, along with ten-year pre- and post-development flows, the release facility's volume-versus-depth performance, maximum water depth in the detention facility, and how the system will be maintained long-term. Culvert design velocity follows the Jefferson Parish manual's criteria unless the outlet ditch is paved. The Director of the Department of Public Works reviews and must approve every covered development before the city issues permits to proceed, making detention-plan approval a hard prerequisite to breaking ground rather than an afterthought.
Violations & Fines
Section 13-53 does not carry its own fine schedule; it is enforced by withholding permits. The Director of Public Works will not approve a covered project, and the city will not issue permits to proceed, until the developer's drainage calculations and detention design meet the section's standards. A developer who begins grading or construction without that sign-off risks a stop-work order and exposure to the Code's general penalty in Section 1-9: a fine of up to $500.00, up to sixty days imprisonment, or both, with each day of continuing violation treated as a separate offense.
Frequently Asked Questions
Does every new building in Kenner need stormwater detention?
What storm event must Kenner detention ponds be designed for?
Who approves a Kenner drainage plan and when?
What happens if a developer skips the detention requirement?
Sources & Official References
Other rules in Kenner
Compare Kenner to another location·View the Louisiana environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.