Ogden, UT Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

SWPPP threshold
Sites larger than one acre
Max cut/fill slope
2:1 ratio absent approval
Stabilization deadline
5 days after clearing/inactivity
Vegetative cover deadline
Must establish within 2 weeks
Enforcement tool
Stop work order, section 9-7B-8

Summary

Ogden City requires an approved storm water pollution prevention plan (SWPPP) for construction disturbing more than an acre, with erosion controls that cap cut and fill slopes at 2:1, demand soil stabilization within five days of clearing, and require vegetative cover to establish within two weeks. The authorized enforcement officer inspects sites and can issue stop work orders under Title 9, Chapter 7, Article B.

9-7B-5: SWPPP DESIGN REQUIREMENTS: ... B. Grading, erosion control practices, sediment control practices, and watercourse crossings shall meet any design criteria established by the authorized enforcement officer pursuant to subsection A of this section, and shall be adequate to prevent transportation of sediment from the site to the satisfaction of the authorized enforcement officer. Cut and fill slopes shall be no greater than two to one (2:1), except as approved by the authorized enforcement officer to meet other community or environmental objectives. ... D. Erosion control practices shall, at a minimum, include the following: 1. Soil stabilization shall be completed within five (5) days of clearing or inactivity in construction. 2. If seeding or another vegetative erosion control method is used, it shall become established within two (2) weeks or the authorized enforcement officer may require the site to be reseeded or a nonvegetative option employed.

Full Breakdown

Article B of Ogden City Code title 9, chapter 7 requires a storm water pollution prevention permit for construction and land disturbing activity, with a full storm water pollution prevention plan (SWPPP) mandatory on sites larger than one acre under section 9-7B-2. Section 9-7B-5 sets the technical design standards. The authorized enforcement officer may adopt administrative design criteria for grading, erosion, sediment control, and watercourse crossings, and cut and fill slopes cannot exceed a two-to-one (2:1) ratio absent approval. Clearing cannot begin until sediment control devices are installed and stabilized.

Once clearing starts, soil stabilization must be completed within five days of clearing or of any inactivity in construction; if a vegetative method like seeding is used, it must establish within two weeks or the site must be reseeded or switched to a nonvegetative option. Off-site soil stockpiles must be stabilized or covered at the end of each workday, and steep slopes or drainageways require specialized stabilization techniques approved by the enforcement officer. Sediment control must include settling basins, sediment traps, and perimeter controls, plus vegetated buffer strips protecting adjacent properties.

Section 9-7B-6 separately requires that erosion, sediment, or pollutant discharge onto public or uncontrolled private property be eliminated to the maximum extent practicable, bars tracking mud or debris onto public rights of way, and requires temporary erosion controls to be removed and any exposed soil permanently stabilized within thirty days after removal. Section 9-7B-7 authorizes the enforcement officer to inspect at each construction stage, and section 9-7B-8 allows a stop work order whenever land disturbance proceeds without a permit or the SWPPP is not implemented.

Violations & Fines

Under section 9-7E-1, violating the erosion and sediment control requirements of chapter 7 is a class B misdemeanor, and civil citations escalate from $125 for a first violation to $500 for repeat noncompliance with a permit, SWPPP, or stop work order. Fines jump to $1,000 per day if the violation involves a direct discharge into the Ogden or Weber Rivers or within 300 feet of them. Each day of continued violation is a separate offense.

Frequently Asked Questions

Does Ogden require a permit before I can start grading a construction site?
Yes. Section 9-7B-2 requires a storm water pollution prevention permit before any construction or land disturbing activity begins in Ogden City, and sites larger than one acre must also submit an approved storm water pollution prevention plan (SWPPP) before the permit is granted.
How steep can cut and fill slopes be on an Ogden construction site?
Section 9-7B-5 caps cut and fill slopes at a two-to-one (2:1) ratio unless the authorized enforcement officer approves a steeper slope to meet other community or environmental objectives, and any approved slope must still be adequate to prevent sediment from leaving the site.
How quickly must a builder stabilize disturbed soil in Ogden?
Section 9-7B-5(D) requires soil stabilization within five days of clearing or of any inactivity in construction. If seeding or another vegetative method is used, it must establish within two weeks or the authorized enforcement officer can require reseeding or a nonvegetative stabilization option instead.
What can the city do if I skip the required erosion controls?
The authorized enforcement officer can issue a stop work order under section 9-7B-8 whenever land disturbing activity proceeds without a permit or the SWPPP isn't being followed, immediately halting the cited work until the violation is corrected and the officer allows work to resume.

Sources & Official References

Other rules in Ogden

All Ogden rules

Compare Ogden to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Ogden, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.