Sammamish, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

ESC required
On every clearing/grading site, permit or not
Excavation limit
10 feet, SMC 16.15.090(2)(a)
Fill limit
5 feet; over 4 feet must be engineered
Permit term
Up to 2 years, renewable every 2 years
Liability insurance
$100,000/$300,000/$50,000, waived under 10,000 cu yd
Work hours
7:00 a.m. to 7:00 p.m.
Wet-season cure period
24 hours after a notice of violation

Summary

Sammamish requires erosion and sediment control on every site that is cleared or graded, whether a permit is needed or not. SMC 16.15.090 makes the property owner responsible for keeping sediment out of drainage facilities, streams, wetlands and neighboring lots, backs it with tighter wet-season rules, and gives violators just 24 hours to fix a failure before work can be shut down.

Any activity that will clear, grade, or otherwise disturb the site, whether requiring a clearing or grading permit or not, shall provide erosion and sediment control (ESC) that prevents, to the maximum extent possible, the transport of sediment from the site to drainage facilities, water resources, and adjacent properties. Erosion and sediment controls shall be applied as specified by the temporary ESC measures and performance criteria and implementation requirements in the City's erosion and sediment control standards.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance O2026-598, and legislation passed through August 18, 2026).

Full Breakdown

090(1) requires ESC on any activity that clears, grades or otherwise disturbs a site, permit or not, applying the City's temporary ESC measures, performance criteria and implementation standards to prevent sediment from reaching drainage facilities, water resources and adjacent properties. 070 for most grading, issued by the Director for up to two years and renewable every two years, with plans typically stamped by a Washington-registered civil engineer or landscape architect. 090(2)(a): excavation cannot exceed 10 feet and fill cannot exceed five feet, though a Type 1, 2 or 3 permit can approve limited deviations, for example where a driveway would otherwise exceed 15 percent slope, and all fill over four feet must be engineered.

080. 120(4) layers on extra scrutiny: the Director must approve clearing and grading in writing based on site conditions and proposed ESC measures, and if silt-laden runoff leaves a site or an approved ESC plan is not maintained, the City issues a notice of violation. Routine ESC maintenance, existing utility upkeep, sites achieving 100 percent on-site infiltration, and unpermitted single-family landscaping stay exempt from the seasonal rules.

Violations & Fines

Starting work without the required clearing and grading permit exposes the responsible party to civil penalties under SMC Title 23. Once a notice of violation issues for an ESC failure, SMC 16.15.120(4)(e) gives the site 24 hours to fix the problem; if it isn't repaired, the inspector can order clearing and grading halted, aside from ESC repair and maintenance work, until the following March 31, and civil penalties continue to accrue under the City's compliance code.

Frequently Asked Questions

Do I need a permit to clear or grade my Sammamish property?
Yes in most cases. SMC 16.15.070 requires a clearing and grading permit from the Director before any clearing or grading begins, unless the work is specifically exempted elsewhere in Chapter 16.15. The Director can require plans stamped by a Washington-registered civil engineer or landscape architect, and issued permits are valid up to two years with renewal available every two years while the work continues.
How much can I cut or fill without extra engineering?
SMC 16.15.090(2)(a) caps ordinary excavation at 10 feet and fill at five feet. Anything beyond that, or any fill over four feet, needs written engineering analysis and review through a Type 1, 2 or 3 permit, and deviations cannot encroach into required structure setbacks or a retained tree's protected root zone.
What happens if my construction site lets sediment run off during the rainy season?
The City issues a notice of violation under SMC 16.15.120(4). You get 24 hours to correct the erosion control problem; if it isn't fixed, an inspector's notice and order can halt all clearing and grading, except erosion control repair, until the following March 31.
Does a grading permit require insurance?
Yes. SMC 16.15.080 requires the permittee to carry liability insurance of $100,000 per individual, $300,000 per occurrence, and $50,000 in property damage, naming the City of Sammamish as an additional insured. The requirement is waived for projects moving fewer than 10,000 cubic yards of material.

Sources & Official References

Other rules in Sammamish

All Sammamish rules

Compare Sammamish to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Sammamish, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in King County handle erosion control.

Renton, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Kent, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions
Seattle, WA
Some Restrictions