Auburn, WA Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard requirement
- Base flood elevation plus 1 foot (FPE)
- Governing section
- ACC 15.68.130
- Enforcing official
- Director of community development (floodplain administrator)
- Permit expiration
- 180 days if construction not started
- Appeal body
- Auburn hearing examiner
Summary
Auburn requires new construction in the Special Flood Hazard Area to be built to a flood protection elevation one foot above the base flood elevation. The floodplain administrator, the city's director of community development, enforces the standard under ACC 15.68.130 before issuing a floodplain development permit.
A. The base flood elevation for the SFHAs incorporated in ACC 15.68.120(A) shall be utilized.
B. The flood protection elevation (FPE) shall be the base flood elevation plus one foot.
C. The floodway shall be as delineated on the Flood Insurance Rate Map.
D. Where base flood elevation and floodway data have not been provided in Special Flood Hazard Areas, the floodplain administrator or designee shall obtain, review and reasonably utilize any base flood elevation and floodway data available from a federal, state or other source.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 7023, passed July 6, 2026).
Full Breakdown
130, the base flood elevation for Special Flood Hazard Areas identified in the FEMA Flood Insurance Studies for King County (dated August 19, 2020) and Pierce County (dated March 7, 2017) governs all development review in Auburn. The code sets the flood protection elevation, the freeboard standard, at the base flood elevation plus one foot, meaning a structure's lowest floor must sit at least one foot above the mapped base flood elevation to satisfy the city's floodplain rules. The floodway itself is fixed by the boundaries delineated on the Flood Insurance Rate Map.
130(D) directs the floodplain administrator or a designee to obtain and reasonably rely on the best available data from a federal, state, or other qualified source rather than let the project proceed unregulated. 170 requires permit applicants to submit a current elevation certificate showing the proposed elevation of the lowest floor in relation to mean sea level, plus an engineering analysis showing no rise in base flood elevation for any work proposed within a floodway. 190 designates the director of community development as floodplain administrator, with authority to grant or deny floodplain development permits and to delegate administration of the chapter. 180, though the administrator may authorize extensions where delay is beyond the applicant's control. 120(A)(5).
Violations & Fines
Building below the required flood protection elevation without a floodplain development permit violates ACC 15.68.160, which requires a permit before any construction or development begins in the Special Flood Hazard Area or Protected Area. Enforcement runs through the community development department; the floodplain administrator can deny or condition permits and require elevation certificates to confirm compliance before approving occupancy.
Frequently Asked Questions
How much freeboard does Auburn require above base flood elevation?
Who decides the base flood elevation for a specific Auburn property?
What happens if base flood elevation data is missing for a site?
Sources & Official References
Other rules in Auburn
Compare Auburn to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in King County handle flood elevation requirements.