Milton, WI Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Flood protection elevation
- 2 feet of freeboard above regional flood
- Floodfringe fill setback
- Fill extends 15+ feet beyond structure
- Floodfringe fill height
- At least 1 foot above regional flood elevation
- AO/AH zone standard
- Highest of 3 elevation tests, Sec. 79-81
- Chapter readopted
- September 15, 2015 ordinance
- Map changes require
- DNR and FEMA letter of map change
- Appeals body
- Board of adjustment/appeals, Sec. 79-123
Summary
Chapter 79 of the Milton Code sets a two-foot freeboard above the regional flood elevation as the city's flood protection elevation. New and substantially improved homes in the floodfringe must place their lowest floor at or above that elevation on fill, and structures in AO or AH zones must clear whichever is higher: the flood protection elevation, two feet above adjacent grade, or the FIRM depth.
Flood protection elevation. An elevation of two feet of freeboard above the water surface profile elevation designated for the regional flood. (Also see: "Freeboard") ... (1)Residential uses. Any structure, including a manufactured home, which is to be newly constructed, or moved into the floodfringe shall meet or exceed the following standards. Any existing structure in the floodfringe must meet the requirements of article VI, nonconforming uses;a.The elevation of the lowest floor shall be at or above the flood protection elevation on fill unless the requirements of subsection (1)b. can be met. The fill shall be one foot or more above the regional flood elevation extending at least 15 feet beyond the limits of the structure ... (1)In AO/AH zones the structure's lowest floor must meet one of the conditions listed below whichever is higher:a.At or above the flood protection elevation; orb.Two feet above the highest adjacent grade around the structure; orc.The depth as shown on the FIRM.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 21 Update 2).
Full Breakdown
The City of Milton's floodplain zoning ordinance, readopted in its entirety on September 15, 2015 under the authority of Wis. 23 and the state floodplain mandate in Wis. 30, defines 'flood protection elevation' in Sec. 79-6 as two feet of freeboard above the water surface profile elevation for the regional flood, a margin meant to absorb ice jams, debris, wave action and the effects of watershed urbanization that the calculated flood level does not capture. That definition drives the construction standards in Article IV. Under Sec.
79-63(1)(a), any structure newly built or moved into the floodfringe district, including a manufactured home, must have its lowest floor at or above the flood protection elevation on fill, with the fill extending at least 15 feet beyond the structure and rising at least one foot above the regional flood elevation; a basement or crawlway floor may instead sit at the regional flood elevation only if it is dry floodproofed up to the flood protection elevation, and no basement floor is ever allowed below the regional flood elevation.
Accessory structures need their lowest floor at or above the regional flood elevation under Sec. 79-63(2)(a). In the general floodplain district's AO and AH zones, Sec. 79-81(c)(1) requires the lowest floor to meet whichever standard is highest: the flood protection elevation, two feet above the highest adjacent grade, or the flood depth shown on the FIRM. The floodway district, mapped as AE zones, layers on stricter limits: Sec. 79-102 bars any enclosed foundation area below the flood protection elevation unless it is built of flood-resistant material with flood-vent openings and limited to parking, access or storage.
Any map amendment changing these elevations needs DNR and FEMA review under the letter of map change process described in Sec. 79-5(b) before a land use permit can issue.
Violations & Fines
A structure without documented lowest-floor elevation, a floodproofing certificate or required floodway calculations is presumed in violation under Sec. 79-6's definition of 'violation.' The zoning administrator investigates and refers violations to the municipal attorney for prosecution and reports actions to the DNR regional office under Sec. 79-121(a)(6). Appeals and variance requests go to the board of adjustment/appeals under Sec. 79-123.
Frequently Asked Questions
What is Milton's flood protection elevation?
How high must a new house be built in the floodfringe?
What if my lot is in an AO or AH zone?
Can a basement be built below the regional flood elevation?
Sources & Official References
Other rules in Milton
Compare Milton to another location·View the Wisconsin environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.