Montgomery, AL Environmental Rules: Flood Elevation Requirements (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Freeboard required
2 ft above base flood elevation
Applies to
New construction & substantial improvements in SFHA
Non-residential alternative
Dry floodproof to 2 ft, PE/architect certified
Critical facilities
4 ft above BFE if built in SFHA
Permit authority
City floodplain administrator
Cumulative damage window
10-year lookback for 50% threshold

Summary

Montgomery requires new construction and substantial improvements in mapped flood hazard areas to elevate the lowest floor at least two feet above the base flood elevation. The floodplain administrator issues the required development permit, and non-residential buildings may dry-floodproof to the same two-foot freeboard instead of elevating.

(1)Residential and non-residential structures. Where BFE data is available, new construction and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than two feet above the base flood elevation (also referred to as the design flood elevation). Should solid foundation perimeter walls be used to elevate a structure, openings sufficient to facilitate the unimpeded movements of flood waters shall be provided in accordance with standards of division 4, subsection 5-652(4). Manufactured homes must also meet the two feet freeboard requirement.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 27).

Full Breakdown

Article X of Chapter 5 implements the National Flood Insurance Program locally. Section 5-652(1) requires that in all special flood hazard areas designated A, AE, or AH, new construction and substantial improvement of any structure or manufactured home shall have the lowest floor, including basement, elevated no lower than two feet above the base flood elevation, also referred to as the design flood elevation. That two-foot cushion is Montgomery's freeboard, defined in Section 5-605 as a safety margin above the calculated flood level. Manufactured homes must meet the same two-foot freeboard.

If solid perimeter foundation walls are used, the walls need flood openings sized to let water pass through automatically, per Section 5-652(4). Non-residential structures may dry-floodproof instead of elevating under Section 5-652(2): the building and its utilities must be watertight to two feet above the base flood elevation, with the design certified by a professional engineer or architect licensed in Alabama. Critical facilities such as hospitals and fire stations must clear the special flood hazard area entirely, or if built inside it, elevate the lowest floor four feet above the base flood elevation.

Every property owner in a special flood hazard area needs a floodplain development permit before building, issued by the floodplain administrator under Sections 5-618 and 5-637, and the administrator tracks substantial-damage determinations over a ten-year lookback under the article's cumulative-damage rule.

Violations & Fines

Building or substantially improving a structure in a mapped flood hazard area without a floodplain development permit is a violation the floodplain administrator can flag with a stop-work order and notice of violation under Section 5-638. Section 5-623 sets penalties for violating the floodplain article, and noncompliant elevation or floodproofing can also jeopardize a structure's National Flood Insurance Program coverage.

Frequently Asked Questions

How high above flood level must a new Montgomery home be built?
At least two feet above the base flood elevation for the lowest floor, including any basement, under Code Section 5-652(1). That two-foot cushion, called freeboard, applies to new construction and substantial improvements alike in mapped A, AE, and AH flood zones.
Can a commercial building in Montgomery's floodplain skip elevating?
Yes, if it dry-floodproofs instead. Section 5-652(2) lets non-residential buildings stay watertight to two feet above the base flood elevation rather than raising the structure, but a professional engineer or Alabama-licensed architect must certify the design.
Who issues a floodplain development permit in Montgomery?
The city's floodplain administrator, under Sections 5-618 and 5-637, reviews and issues the permit required before any construction, fill, or other development begins in a special flood hazard area, and inspects the area for unpermitted work.

Sources & Official References

Other rules in Montgomery

All Montgomery rules

Compare Montgomery to another location·View the Alabama environmental rules overview

Get notified when Flood Elevation Requirements in Montgomery, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.