Berwyn, IL Environmental Rules: Stormwater Management (2026)
Key Facts
- Design storm
- 50-year, 24-hour return frequency event
- Maximum discharge rate
- 0.15 cubic feet per second per acre
- Plan preparer
- Professional engineer registered in Illinois
- Sheet flow
- Impervious runoff may not sheet flow to the public right-of-way
- Fee-in-lieu approval
- Zoning, Planning, and Development Commission
- Waiver recording
- Cook County Recorder of Deeds, at owner's expense
Summary
In the City of Berwyn, Illinois, § 1250.03 requires covered developments to manage the 50-year, 24-hour storm, hold discharge to 0.15 cubic feet per second per acre, and keep runoff from impervious surface off the public right-of-way. A property that cannot fit the controls can apply for a fee-in-lieu through the Zoning, Planning, and Development Commission.
(A) Purpose. ... The purpose of this section is to establish stormwater management regulations that reduce the volume and rate of stormwater runoff entering the storm sewer system and help prevent flood damages. ... (1) Runoff detention. ... Detention shall be achieved through incorporation of green infrastructure, post-construction stormwater management measures, and BMPs designed to increase permeable areas and to reduce pollution. ... (2) Discharge rate. The maximum allowable discharge rate shall be 0.15 cubic feet per second per acre (cfs/ac). The maximum discharge rate (cfs) from the regulated development shall be based on the maximum release rate (cfs/ac) times the disturbed land area (ac). (3) Sheet flow. Runoff from impervious surface area shall not sheet flow to the public right-of-way.
Full Breakdown
Section 1250.03 of the Berwyn Code of Ordinances states its purpose as reducing the volume and rate of stormwater runoff entering the storm sewer system and helping prevent flood damages. It applies to development meeting the § 1250.01(B) criteria: new developments needing site plan approval, planned developments, and new or expanded parking lots reaching 15 spaces. It does not replace controls required by any other agency. If another agency's stormwater rules also apply, both sets must be met, and where they conflict the more restrictive provision governs.
The design storm is the 50-year, 24-hour return frequency event. Detention is to be achieved through green infrastructure, post-construction stormwater management measures and BMPs designed to increase permeable areas and reduce pollution. The maximum allowable discharge rate is 0.15 cubic feet per second per acre, multiplied by the disturbed land area, and runoff from impervious surface cannot sheet flow to the public right-of-way.
A stormwater management plan under § 1250.01(E) must be prepared by a professional engineer registered in Illinois and approved by the Zoning Administrator. It shows sub-catchment areas, retention and detention BMP capacities, itemized drainage costs, an implementation timeline and an operations and maintenance schedule for each BMP. Site BMPs consist primarily of green infrastructure.
A property that cannot fit the controls on the lot can seek a fee-in-lieu. The Zoning, Planning, and Development Commission weighs whether approval will facilitate new development or redevelopment and whether lot size and configuration constrain the controls. Public Works calculates the fee for construction and ongoing maintenance, payments go into a dedicated stormwater management fund, and the certificate of waiver is recorded with the Cook County Recorder of Deeds at the owner's expense, with full payment made before a certificate of occupancy issues. Private facilities stay the owner's responsibility under a signed, notarized O&M plan and a recorded maintenance easement that gives the city inspection access.
Violations & Fines
Under § 1250.01(C), landscape elements and stormwater management facilities must be fully installed before an occupancy permit issues. Failure to implement the approved plan or maintain installed elements is cause for revocation of the occupancy permit and/or fines and penalties. The passages read state no dollar figure. Section 1250.03(C)(5)(b) also bars discharge from facilities that exceeds design criteria or contributes to water quality standard violations.
Frequently Asked Questions
What is the stormwater discharge limit in Berwyn?
Can a Berwyn property pay a fee instead of building stormwater controls?
Who maintains a private stormwater facility in Berwyn?
Sources & Official References
Other rules in Berwyn
Compare Berwyn to another location·View the Illinois environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Stormwater Management in Nearby Cities
How other cities in Cook County handle stormwater management.