Oldham County, KY Environmental Rules: Stormwater Management (2026)
Key Facts
- Plan threshold
- 1 acre or more of disturbance
- Reviewing office
- Oldham County Engineer
- Water quality event
- 80th percentile, 0.6 inch rainfall
- BMP drain time
- 48 hours maximum
- Daily fine
- $75 to $150 per day
Summary
Unincorporated Oldham County requires a reviewed stormwater management plan and permanent BMPs for any development disturbing an acre or more. Design storms, a water-quality volume standard and a recorded maintenance agreement are mandatory, with violations fined $75 to $150 per day.
(B) Any development activity that involves land disturbance of one acre or more shall submit to the County Engineer, prior to development, a stormwater management plan showing location of post-construction best management practices (BMPs) prior to any construction activity. ... The WQv used for sizing green infrastructure BMPs shall be computed as follows: ... The drain time for all green infrastructure BMPs shall be 48 hours at a maximum, such that there is no standing or residual water in the BMP following the WQv rainfall event.
Full Breakdown
Chapter 154, Post-Construction Stormwater, Pollutants and Sediment, governs stormwater management in unincorporated Oldham County and in any incorporated area that is a co-permittee on the county's KPDES MS4 permit (§ 154.01). Under § 154.03, any new development or redevelopment disturbing one acre or more, or part of a larger common plan disturbing an acre or more, must submit a stormwater management plan to the County Engineer before construction, sealed by a Kentucky-licensed professional engineer, and obtain a soil and erosion control permit. Design criteria in § 154.05 require the ten-year storm for public storm sewers and channels, the 100-year storm as a check, and post-development peak flow rates held at or below pre-development rates for the two-year, ten-year and 100-year storms.
Green infrastructure BMPs must capture the water quality volume from the 80th percentile precipitation event, equivalent to 0.6 inches of rainfall, and drain within 48 hours. Every stormwater facility must be covered by a recorded maintenance agreement running with the land, binding successors and any homeowners association, per § 154.09, and easements permitting county inspection must be granted and recorded with the County Clerk.
Violations & Fines
Under § 154.08, the county issues a written notice of violation to the developer, property owner or assignees for noncompliance during construction, with a deadline to correct; the county may also stop work, issue a citation before the Code Enforcement Board, or draw on the posted surety to complete corrective work. Conviction carries a fine of not less than $75 nor more than $150 per day per offense, measured from the notice date, with each day a separate offense. Section 154.10 applies the same notice-and-correction process after construction for facility maintenance failures, with unpaid corrective costs collectible after 30 days.
Frequently Asked Questions
When does a development need a stormwater management plan in unincorporated Oldham County?
What water quality standard must Oldham County stormwater facilities meet?
Who maintains a stormwater detention pond after a subdivision is built in Oldham County?
Sources & Official References
Other rules in Oldham County
Compare Oldham County to another location·View the Kentucky environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.