Plantation, FL Environmental Rules: Stormwater Management (2026)

Heavy Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Governing Article
Ch. 9, Art. II (Ord. 2024-001)
Zero Discharge
25-year, three-day storm event
Impervious Cap
65 percent of site area
Water Quality
First inch of runoff detained
Districts
SFWMD, OPWCD and PAID

Summary

Chapter 9, Article II, rewritten by Ordinance 2024-001, applies to every area inside the city. Site perimeter grades must allow zero discharge in a 25-year, three-day storm, and impervious cover is capped at 65 percent.

the site perimeter grade shall be designed to allow zero discharge during a 25-year, three-day storm event, and pre-development discharge shall be less than or equal to post-development discharge for the 100-year storm event

Source: City of Plantation Code of Ordinances (Municode)View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 30 Update 1).

Full Breakdown

The drainage level of service standards are specific. Emergency access roadways must carry their full width above the ten-year, one-day storm elevation, eighteen inches below the 100-year flood elevation, or 5.5 feet NAVD, whichever is greater; other roads need half their width above that mark. For water quality, wet detention must hold the first inch of runoff from the developed project, or 2.5 inches times the percentage of imperviousness, whichever is greater, with dry detention at 75 percent and retention at 50 percent of that volume. Every project also has to satisfy the SFWMD, the Old Plantation Water Control District and the Plantation Acres Improvement District.

Violations & Fines

No certificate of occupancy or completion issues until the applicant has letters of approval from every regulatory agency plus the City Engineer and Building Official. Code enforcement fines reach $1,000 a day, and $5,000 a day for repeats.

Frequently Asked Questions

Do I need approval for drainage work in Plantation?
Yes. Any construction, alteration, operation, maintenance, removal or abandonment affecting surface water management requires approval from the Engineering Department and the appropriate drainage district, and city approval does not replace other permits.
How much of my site can be impervious?
Section 9-23 restricts impervious area, including roofs and pools, to sixty-five percent, and to the assumptions or other limitations of the Master Drainage Permit.

Sources & Official References

Other rules in Plantation

All Plantation rules

Florida rules heatmap·Compare Plantation to another location·View the Florida environmental rules overview

Get notified when Stormwater Management in Plantation, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities

How other cities in Broward County handle stormwater management.

Hollywood, FL
Some Restrictions
Pompano Beach, FL
Some Restrictions
Miramar, FL
Some Restrictions
Coral Springs, FL
Some Restrictions
Fort Lauderdale, FL
Some Restrictions
Pembroke Pines, FL
Significant Restrictions