Utah Construction Stormwater and Erosion Control (Utah Code 19-5-107)

Some RestrictionsApplies statewide across Utah (2026)

Key Facts

Permit trigger
Disturbing 1 acre or more
Permit type
UPDES Construction General Permit
Civil penalty
Up to $10,000 per day
Enforcing agency
DEQ Division of Water Quality
Governing statute
Utah Code 19-5-107
Last verified: July 31, 2026

Summary

Land-disturbing construction of one acre or more in Utah must obtain a UPDES Construction General Permit from the Division of Water Quality before ground is broken, and control erosion and sediment so runoff does not carry pollutants into waters of the state.

(1)(a) Except as provided in this chapter or rules made under it, it is unlawful for any person to discharge a pollutant into waters of the state... (3) It is unlawful for any person, without first securing a permit from the director, to: (a) make any discharge or manage sewage sludge not authorized under an existing valid discharge permit; or (b) construct, install, modify, or operate any treatment works or part of any treatment works...

Full Breakdown

Utah Code 19-5-107 makes it unlawful to discharge a pollutant into waters of the state, or to make any discharge, without first securing a permit from the director. Sediment-laden stormwater from construction is such a discharge, so the Utah Division of Water Quality, part of the Department of Environmental Quality, requires operators disturbing one acre or more, including smaller lots inside a larger common plan of development, to obtain the UPDES Construction General Permit and implement a Storm Water Pollution Prevention Plan with erosion and sediment controls before soil is disturbed. The Water Quality Board sets the rules, and each discharge permit runs for a fixed term not exceeding five years.

Violations & Penalties

Discharging construction stormwater without a permit, or violating permit conditions, carries a civil penalty not to exceed $10,000 per day of violation under Utah Code 19-5-115, plus possible stop-construction orders and criminal fines up to $25,000 per day for negligent discharges.

Frequently Asked Questions

Who needs a Utah construction stormwater permit?
Any operator disturbing one acre or more of land, or a smaller parcel that is part of a larger common plan of development, must obtain the UPDES Construction General Permit before disturbing soil.
What is the penalty for discharging without a permit?
Utah Code 19-5-115 sets a civil penalty not to exceed $10,000 per day of violation, and criminally negligent illegal discharges can bring fines up to $25,000 per day.
Which agency enforces it?
The Utah Division of Water Quality, within the Department of Environmental Quality, issues the permit and enforces the Water Quality Act under authority delegated by the EPA.

Sources

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.