Key Facts

Permitting authority
Building Department Administrator
Exempt work
Nonstructural repairs; sheds under 12 ft / $100
Residential insurance minimum
$300,000/$600,000 liability coverage
Permit validity
2 years, one 1-year extension available
Unpermitted-work fee
Triple the standard permit fee

Summary

Glen Cove requires a separate building permit from the Building Department Administrator for nearly every construction project. City Code § 111-9 exempts only nonstructural repairs and small temporary sheds under 12 feet and $100 in cost.

No person, firm or corporation shall commence the erection, construction, enlargement, alteration, removal, improvement, demolition, conversion or change in the nature of the occupancy of any building or structure, or cause the same to be done, without first obtaining a separate building permit from the Building Department Administrator for each such building or structure; except that no building permit shall be required for the performance of ordinary repairs which are not structural in nature or an open or temporary shed not over 12 feet in height and of an estimated cost not exceeding $100.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 5003439; v76 updated 2026-08-26; through 08-26-2026).

Full Breakdown

Section 111-9 of the Glen Cove City Code bars anyone from commencing the erection, construction, enlargement, alteration, removal, improvement, demolition, conversion or occupancy change of any building or structure without first obtaining a separate building permit from the Building Department Administrator for each structure. The only exemptions are ordinary nonstructural repairs and an open or temporary shed no more than 12 feet high costing no more than $100 to build. Applications must include duplicate ink or blueprint drawings and specifications, floor loads, occupancy details and, when required, a real estate survey, and must comply with § 280-10 of the Zoning chapter; every fact in the application must be sworn under oath.

For residential construction, § 111-9(G) additionally requires the contractor's Nassau County home improvement license number, proof of active New York workers' compensation coverage, and personal and property liability insurance of at least $300,000 per occurrence and $600,000 aggregate before the application can even be deemed complete. A homeowner who wants to do the work personally can be tested by the Building Department Administrator on construction technology and code knowledge under § 111-9(H). Under § 111-10, building without a permit does not excuse the requirement: the city instead charges triple the standard processing fee once caught.

Permits issued under § 111-11 expire after two years if construction and a certificate of occupancy are not completed, with one one-year extension available from the City Council for extenuating circumstances, and lapse entirely if no work begins within one year.

Violations & Fines

Commencing construction, alteration, demolition or occupancy change without a building permit, or continuing after a permit is revoked under § 111-13, is a violation of Chapter 111 punishable under § 111-24: not less than $1,000 nor more than $2,000 for a first offense, rising to $2,000-$3,500 and $3,500-$5,000 for repeat offenses within five years, plus up to 15 days imprisonment, with each week of continued violation a separate offense.

Frequently Asked Questions

What work in Glen Cove needs a building permit?
Any erection, construction, enlargement, alteration, removal, improvement, demolition, conversion or occupancy change of a building or structure, per § 111-9(A), except ordinary nonstructural repairs or a temporary shed under 12 feet and $100 in cost.
Can I build without a permit and just pay a fee later?
No, it stays unlawful, but § 111-10(A) does specifically address it: if you build without a permit, the city will not issue one retroactively until you pay three times the standard processing fee, on top of any penalty.
Does a homeowner doing their own work need a contractor license?
No, but § 111-9(H) requires the Building Department Administrator to test the homeowner's competence in construction technology and code requirements before issuing the permit.
How long is a Glen Cove building permit valid?
Two years from issuance under § 111-11(B); the City Council can grant one additional one-year extension for extenuating circumstances, and the permit voids if no work starts within one year.

Sources & Official References

Other rules in Glen Cove

All Glen Cove rules

New York rules heatmap·Compare Glen Cove to another location·View the New York building safety overview

Get notified when Building Permits in Glen Cove, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.