Glynn County, GA Building Safety: Building Permits (2026)
Key Facts
- Code adopted
- 2006 IBC with Georgia amendments
- Enforcing office
- Glynn County Building Official
- Residential base fee
- $300 up to 1,700 sq ft
- Late-permit penalty
- Fee doubled
- Appeal window
- 30 days
- Applies to
- Unincorporated county only
Summary
Any construction, alteration, repair, or demolition of a building in unincorporated Glynn County must follow the 2006 International Building Code with Georgia amendments, administered by the Glynn County Building Official. Starting work before the permit issues doubles the permit fee, and violations are prosecuted as misdemeanors.
There is hereby adopted by the Board of Commissioners, Glynn County, for the purpose of prescribing regulations governing the construction, alteration, repair, use and occupancy, location, maintenance, removal and demolition of every building or structure, ... that certain Code known as the International Building Code, being particularly the 2006 edition of the International Building Code with Georgia Amendments ... from and after the effective date of the provisions thereof shall be in full force and effect within the area of Glynn County, Georgia, lying outside the corporate limits of the City of Brunswick. ... d.Where work for which a permit is required by the Code is commenced prior to obtaining required permit, the fee specified shall be doubled, but the payment of such double fee shall not relieve any person from fully complying with the requirements of this Code in the execution of the work or from any other penalties prescribed herein. ... a.Violations of this ordinance and the provisions of said Building Code shall be punished as for a misdemeanor according to the provisions of O.C.G.A. § 36-13-12.
Full Breakdown
Section 2-5-20 adopts the 2006 edition of the International Building Code with Georgia Amendments for the part of Glynn County outside the City of Brunswick's limits, and the code updates automatically whenever the State of Georgia adopts a new amendment, except where the Board of Commissioners has separately changed it. Section 2-5-21 defines 'Building Official' to mean the Glynn County Building Official, who administers and enforces the code under Section 2-5-23. That section also blocks progress past the foundation on any new construction served by community water or wastewater until the utility provider has approved the service plans and, if required, a water meter has been purchased and installed.
00 up to 1,700 square feet, then a per-square-foot rate above that, with separate rates for enclosed and covered space and for commercial occupancy types keyed to square footage. 00. Section 2-5-24(d) is the enforcement lever behind the permit requirement: if work needing a permit starts before the permit is obtained, the fee is doubled, though paying double does not excuse the applicant from otherwise following the Code or from any other penalty. Appeals of the Building Official's decisions go to the Board of Adjustments and Appeals under Section 2-5-25, and Section 2-5-22 shortened the code's own appeal window from 90 days to 30 days after a decision.
Violations & Fines
Section 2-5-28(a) makes violating the building ordinance or the adopted Building Code a misdemeanor under O.C.G.A. § 36-13-12. Beyond criminal prosecution, the Building Official, acting for the Board of Commissioners, or any neighboring property owner harmed by the violation, can seek an injunction, mandamus, or other court action to stop or correct the unpermitted work under Section 2-5-28(b).
Frequently Asked Questions
What happens if I start building before getting a permit?
Does this building code apply inside Brunswick?
How much does a residential building permit cost?
Sources & Official References
Other rules in Glynn County
Compare Glynn County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.