Smyrna, GA Building Safety: Building Permits (2026)
Key Facts
- Permit trigger
- Erect, move, add to or structurally alter a building
- Issuing officer
- Building inspector (chief building official waives plans)
- Plans
- Duplicate sets, sealed by architect, engineer or land surveyor
- Residential permit validity
- Six months, expires if not inspected
- Other permit validity
- Two years, expires if not begun in six months
- Appeal
- To the mayor and council (§ 18-37)
Summary
In the City of Smyrna, Georgia, Appendix A § 1302 requires a building permit from the building inspector before any building or other structure is erected, moved, added to or structurally altered. The permit issues only if the development conforms to the zoning ordinance. Permits expire after six months for residential buildings and after two years for other buildings.
No building or other structure shall be erected, moved, added to, or structurally altered without a building permit issued by the building inspector. A building permit shall be issued only if the proposed development is in conformity with the provisions of this ordinance.
Full Breakdown
Section 1302 of the Smyrna Zoning Ordinance, Appendix A of the city code, covers four actions: erecting, moving, adding to and structurally altering a building or other structure. Each needs a permit issued by the building inspector, and the permit issues only if the proposed development conforms to the ordinance. Section 1301 names the building inspector as the officer who issues grading and building permits and certificates of occupancy and who makes field inspections against the approved site plan.
Applications go to the building inspector under § 1304. A permit application must come with complete plans in duplicate, drawn to scale, prepared by an architect, engineer or land surveyor whose state registration is current and whose seal is affixed. Residential stand-alone permits for plumbing, electrical and mechanical work, excluding structural work, do not require plans unless the chief building official asks for them, and the chief building official can waive plans when the work does not need them to show compliance with the current building code. The plans show the shape and dimensions of the lot, the sizes and locations of existing buildings, and the shape, size, height, use and location of the proposed building.
Grading is a separate permit. Under § 1303, no grading or other alteration of the land starts without a grading permit, and the site development plan must include a grading plan, erosion and sedimentation control plan, tree preservation plan, future building locations, parking layout and storm drainage design.
Validity is short. Under § 1305, a building permit for other than residential construction is valid for two years, and it expires if work has not begun within six months or is not completed within two years. A residential building permit is valid for six months and expires if the work has not been inspected within that time. Section 1306 requires a certificate of occupancy, applied for at the same time as the building permit and issued within ten days after work is completed in conformity with the ordinance.
Chapter 18 adopts the Standard Building Code, the CABO One- and Two-Family Dwelling Code and the Standard Unsafe Building Abatement Code, latest editions as adopted by the state (§ 18-32). A denial of a permit or other adverse decision by the building inspector can be appealed to the mayor and council (§ 18-37).
Violations & Fines
Violating the zoning ordinance, including building without the required permit, is a misdemeanor under § 1307, punished on conviction by a fine of at least $200.00 and not more than $500.00 for each offense, and each day is a separate offense. Violations of the building codes are punished as provided in § 1-8 under § 18-32(b). Section 1308 adds injunction and abatement actions.
Frequently Asked Questions
What work needs a building permit in Smyrna?
Do I need plans for a stand-alone plumbing or electrical permit?
How long does a Smyrna building permit last?
What if the building inspector denies my permit?
Sources & Official References
Other rules in Smyrna
Compare Smyrna to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities