Key Facts

Permit issuer
Electrical inspector (§ 18-96)
Who can hold a permit
Licensed electrical contractor, or a homeowner working alone in own home
Adopted code
National Electrical Code, latest edition as adopted by the state
Permit scope (§ 18-100)
One designated job and one building per permit
Temporary wiring (§ 18-114)
Permit issued for no more than 90 days
Fee authority (§ 18-101)
Schedule approved by Mayor and Council

Summary

In the City of Smyrna, Georgia, no wiring installation or alteration in a building or structure for light, heat or power, and no increase in rated load, can proceed without a permit from the electrical inspector. Permits go only to a licensed electrical contractor or to a person working in his or her own home without help, under the National Electrical Code.

No installation or alteration shall be made of the wiring in any building or structure for light, heat or power, or increase in the rated load, as fixed by the city electrical code, carried by such wires, without a permit therefor from the electrical inspector. Such permit shall be issued only to a licensed electrical contractor, or to a person doing work in his/her own home without the assistance of any other person.

Full Breakdown

Section 18-96 requires a permit from the electrical inspector for any installation or alteration of the wiring in a building or structure for light, heat or power, or any increase in the rated load carried by those wires. The permit is issued only to a licensed electrical contractor, or to a person doing work in his or her own home without the assistance of any other person. Section 18-61 adopts the National Electrical Code published by the National Fire Protection Association, in the latest edition as adopted by the state, with three copies on file in the office of the building inspector.

Section 18-97 requires an application on forms furnished by the city before any work begins, with an accurate and detailed account of the work. Under § 18-98 the applicant files a written statement giving the location by street and number, the name of the person for whom the work is done and the scope of the work, then pays the fees. The electrical inspector issues the permit after approving the application and can require a general plan of construction. One permit covers one designated job and one building (§ 18-100), and added or increased load needs a new application (§ 18-99).

Fees are approved by the Mayor and Council, with the schedule kept on file in the building inspector's office (§ 18-101). Minor repairs involving no new work are exempt, but not new circuits or extensions of circuits (§ 18-69). Temporary wiring needs a written permit and lasts no more than 90 days (§ 18-114).

Violations & Fines

Anyone who violates the electrical code is punished as provided in § 1-8, which sets a fine not exceeding $1,000.00, up to six months in the city jail, probation up to six months, community service up to 30 days, or a combination, with each day a separate offense. A person who does not correct defects within five days of notice gets no further permit (§ 18-66). The electrical inspector can also condemn unsafe wiring and order current discontinued after three days' notice (§ 18-84).

Frequently Asked Questions

When is an electrical permit required in Smyrna?
Section 18-96 requires a permit from the electrical inspector for any installation or alteration of wiring in a building or structure for light, heat or power, and for any increase in the rated load carried by those wires. Minor repairs involving no new work, alteration or change are exempt under § 18-69, but new circuits and circuit extensions are not.
Can a homeowner pull their own electrical permit?
Yes, within a narrow limit. Section 18-96 says the permit is issued only to a licensed electrical contractor, or to a person doing work in his or her own home without the assistance of any other person. Anyone else needs a licensed electrical contractor to take out the permit.
What information goes on the application?
Section 18-97 requires an application on city forms with an accurate and detailed account of the contemplated work. Section 18-98 adds a written statement of the location by street and number, the name of the person for whom the work is done, and the scope of the wiring, apparatus or fixtures. The electrical inspector can also require a general plan of construction.
How long can temporary electrical service stay in place?
A temporary wiring permit is issued for a period of no more than 90 days under § 18-114. Longer use needs a written extension request from the permit holder, and service is discontinued at expiration unless the electrical inspector approves more time. The application must state the period required and why temporary service is necessary.
Which electrical code does Smyrna enforce?
Section 18-61 adopts the National Electrical Code published by the National Fire Protection Association, in the latest edition as adopted by the state. It controls installation of wiring and wiring devices within the city, subject to Smyrna's own modifications and amendments, and three copies are filed with the building inspector.

Sources & Official References

Other rules in Smyrna

All Smyrna rules

Compare Smyrna to another location·View the Georgia building safety overview

Get notified when Electrical Permits in Smyrna, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Cobb County handle electrical permits.

Acworth, GA
Some Restrictions