Woodland, CA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2025 California Building Code (2024 IBC)
Permit fee source
City of Woodland Comprehensive Fee Schedule
Work-before-permit fee
3x fee (1st offense), 5x (each later offense)
Enforcing official
Woodland Building Official, Section 114
Criminal penalty
Infraction (1st/2nd), misdemeanor (3rd+)
Latest amendment
Ordinance No. 1746, November 18, 2025

Summary

In the City of Woodland, California, work on a building, structure, or its electrical, gas, mechanical, or plumbing systems needs a permit under the city's adopted 2025 California Building Code. Starting work before the permit issues triggers a fee of three times the normal permit fee for a first offense and five times for each later offense, per Woodland Municipal Code § 15.04.030(C).

§ 15.04.020. Violation of codes—Penalties. Violation of any provision of the Codes shall subject the violator to any or all of the following: suit for civil remedy or criminal penalty, or the administrative penalties provided in Chapter 9.20 of the Woodland Municipal Code. The criminal penalty for the first or second offense shall be punishable as an infraction as defined by the California Penal Code, as amended from time to time. The criminal penalty for a third offense or more, shall be punishable as a misdemeanor as defined by the California Penal Code, as amended from time to time. ... Section 109.4 is amended to read as follows: 109.4 Work commencing before permit issuance. Any person who commences work requiring a permit on a building, structure, electrical, gas, mechanical, or plumbing shall be subject to a fee equal to three times the calculated permit fee for the first offense and five times the calculated permit fee for each subsequent offense.

Full Breakdown

Woodland adopted the 2025 California Building Code, incorporating the 2024 International Building Code, as the city's Building Code under Woodland Municipal Code § 15.04.010(a), and set permit fees by referring to the City of Woodland Comprehensive Fee Schedule rather than printing dollar amounts in the code itself, per the local amendment to Section 109.2 in § 15.04.030(B). Section 109.4, amended by § 15.04.030(C), targets anyone who starts work needing a permit, on a building, structure, or its electrical, gas, mechanical or plumbing systems, before the permit is issued: the fee jumps to three times the calculated permit fee for a first offense and five times for each later offense.

Section 114, substituted in full by § 15.04.030(D), gives the Building Official authority to serve a notice of violation ordering the illegal work stopped and the violation abated, and, if that notice is not promptly obeyed, to ask the city attorney to sue to restrain, correct, or abate the violation or to terminate an unlawful occupancy. Anyone who violates the adopted Codes, including by building without a required permit, is also exposed to the citywide penalty structure in § 15.04.020: civil remedy or criminal penalty, or an administrative penalty processed under Chapter 9.20, with a first or second criminal offense charged as an infraction and a third or later offense charged as a misdemeanor under the California Penal Code. These amendments were most recently carried forward by Ordinance No. 1746, adopted November 18, 2025.

Violations & Fines

Building without a required permit exposes the responsible party to triple the calculated permit fee on a first offense and five times the fee for each later offense under § 15.04.030(C)(109.4), plus the Building Official's power to order the work stopped and abated under Section 114. Violations can also be charged criminally: an infraction for a first or second offense, a misdemeanor for a third or more, under § 15.04.020.

Frequently Asked Questions

What work requires a building permit in Woodland?
Any work on a building, structure, or its electrical, gas, mechanical, or plumbing systems needs a permit under the city's 2025 California Building Code, adopted at Woodland Municipal Code § 15.04.010(a); starting that work before the permit issues is itself a separately penalized violation under § 15.04.030(C).
What happens if I start construction before my permit is issued?
Section 15.04.030(C) amends Section 109.4 of the California Building Code so that anyone who commences permit-required work, on a building, structure, or its electrical, gas, mechanical, or plumbing systems, before the permit issues owes three times the calculated permit fee for a first offense, rising to five times the fee for each later offense.
Who decides how much a Woodland building permit costs?
The code itself does not print dollar figures. Section 15.04.030(B) amends Section 109.2 so that permit fees are set in the City of Woodland Comprehensive Fee Schedule, adopted separately by City Council resolution, rather than in the building code text.
Can I be criminally charged for a building code violation?
Yes. Under § 15.04.020, a first or second violation of the adopted Codes is punishable as an infraction under the California Penal Code, and a third or later violation is punishable as a misdemeanor, in addition to any civil remedy or Chapter 9.20 administrative penalty.

Sources & Official References

Other rules in Woodland

All Woodland rules

California rules heatmap·Compare Woodland to another location·View the California building safety overview

Get notified when Building Permits in Woodland, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Yolo County handle building permits.

West Sacramento, CA
Some Restrictions