Skip to main content
CityRuleLookup

Casper, WY Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Certificate required
§ 15.04.090, before use/occupancy change
Occupancy permit steps
§ 15.08.040, final plus final plumbing inspection
Winter exception window
Nov 15 to Mar 1 with roadway conditions
Notice deadline for winter exception
City engineer notified by Oct 15
Penalty
Misdemeanor plus possible contractor license suspension

Summary

Casper bars anyone from using a new building until the building official signs off. Section 15.04.090 requires a Certificate of Occupancy before use or a change in occupancy classification, and Section 15.08.040 spells out the final-inspection steps, including a mandatory final plumbing inspection, before that certificate or an occupancy permit can issue.

Section 111.1 Use or Occupancy—No building or structure shall be used or occupied, and no change in the existing occupancy classification of a building or structure or portion thereof shall be made until the building official has issued a Certificate of Occupancy therefor as provided herein, and providing that all off-site improvements required by the subdivision code have been completed. ... A.No person shall occupy a building for which a building permit is required, prior to obtaining an occupancy permit for the building. An occupancy permit may be issued upon completion of a final inspection of a building, as required by city ordinances, and upon completion of all off-site improvements in a subdivision or construction phase of a subdivision, and upon compliance with all city ordinances, except as provided in subsection B of this section.

Full Breakdown

Casper's amended International Building Code Section 111.1, codified at Section 15.04.090, states that no building or structure shall be used or occupied, and no change in the existing occupancy classification of a building or structure or portion thereof shall be made, until the building official has issued a Certificate of Occupancy, and adds a local condition that all off-site improvements required by the subdivision code must also be complete. Chapter 15.08's occupancy-permit process fills in the mechanics: Section 15.08.040(A) says no one may occupy a building requiring a permit before obtaining an occupancy permit, which issues only after a final inspection required by city ordinance and completion of subdivision off-site improvements.

The section adds a utility-control step unique to Casper: the inspector performing the final plumbing inspection must shut off and lock the water service at the curb stop, and the permit holder must request that final plumbing inspection before occupancy; water service is only restored, and the curb-stop lock removed, at the moment the occupancy permit issues. Subsection B carves out a winter exception for subdivisions completed between November 15 and March 1, letting an occupancy permit issue ahead of full off-site improvements if all-weather roadways are built to the city engineer's and Casper Public Utilities' satisfaction, the responsible party notifies the city engineer by October 15 of its intent, and a maintenance plan with a named responsible person is filed and followed until construction resumes as of March 1.

The engineering department and building official jointly administer this permit chain, and Section 15.08.050 makes any violation of the chapter a misdemeanor with a possible contractor's-license suspension.

Violations & Fines

Occupying a building before the Certificate of Occupancy or occupancy permit issues, or before required final and final-plumbing inspections are complete, is a misdemeanor under Section 15.08.050, punishable per Chapter 1.28 of the Casper Municipal Code. A licensed building contractor who violates the chapter can also have the city suspend or revoke that contractor's license, in addition to any criminal penalty.

Frequently Asked Questions

When does Casper require a Certificate of Occupancy?
Section 15.04.090 says no building may be used or occupied, and no occupancy classification changed, until the building official issues a Certificate of Occupancy, and only after all subdivision off-site improvements required by the subdivision code are complete.
What inspections happen before an occupancy permit issues?
Section 15.08.040 requires a final inspection of the building and a final plumbing inspection before occupancy. The inspector performing the plumbing inspection shuts off and locks the curb-stop water service, which is only turned back on when the occupancy permit is issued.
Can a builder get an occupancy permit before winter improvements are finished?
Yes, under Section 15.08.040(B). If all-weather roadways are completed and approved by the city engineer and Casper Public Utilities, the party notifies the city engineer by October 15, and a maintenance plan is filed, an occupancy permit can issue between November 15 and March 1 ahead of full off-site improvements.

Sources & Official References

Other rules in Casper

All Casper rules

Compare Casper to another location·View the Wyoming building safety overview

Get notified when Building Inspections in Casper, WY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.