Elevator Maintenance

In the City of Noblesville, any building equipped with an elevator that must have a key box under local, state, or national code needs Fire Department approval for the box's location before installation. Once installed, the owner must contact the Noblesville Fire Department to load the required keys, including the elevator door key, equipment room key, and Fire Department emergency access control keys.

Noblesville Elevator Key Box Requirement

Some Restrictions

Noblesville Code of Ordinances § 92.064

§ 92.064 ELEVATOR KEY BOXES. When a building is equipped with an elevator(s) and required by local, state, or national code to install an elevator key box, the owner, or his or her duly authorized agent, shall contact the City of Noblesville Fire Department for approval of the location of the elevator key box. After installation, the owner, or his or her duly authorized agent, shall contact the...

Fire Sprinkler Requirements

Buildings in the City of Noblesville that have a fire sprinkler system must keep specific paperwork on-site under § 92.094 of the Fire Prevention Code: a zone diagram at multi-zone risers, as-built plans and hydraulic calculations for the whole system, and posted instructions for an impairment coordinator when the Indiana Fire Code requires one.

Noblesville Sprinkler System Documentation Duty

Some Restrictions

Noblesville Code of Ordinances § 92.094

§ 92.094 SPRINKLER SYSTEMS. (A) If a sprinkler system has multiple zones, an approved zone diagram or map shall be mounted adjacent to the sprinkler riser. (B) A copy of the as-built sprinkler plans and hydraulic calculations for every sprinkler system shall be kept permanently on-site in an approved location. (C) Instructions for the assignment of an impairment coordinator shall be posted adja...

Building Permits

The City of Noblesville requires a permit before any construction, alteration, repair, or demolition of a building or structure begins, per Noblesville Code of Ordinances § 154.15, with applications reviewed by the Director of Planning and fees paid to the Clerk-Treasurer.

Noblesville Building Permit Requirement

Some Restrictions

Noblesville Code of Ordinances §§ 154.15, 154.20

A permit shall be obtained before beginning construction, alteration, repair, or demolition of any building or structure, using application forms furnished by the Director, and all fees required by this code shall be paid to the Clerk-Treasurer. Application fees shall be determined in accordance with Ordinances 1513 and 1522, as amended. ... The work or use authorized by a building permit shall...

Electrical Permits

The City of Noblesville adopts the Indiana Electrical Code under Article 17 of Title 675 of the Indiana Administrative Code by reference into its Building Code, per Noblesville Code of Ordinances § 154.04(A)(4), and a permit is required before electrical work begins under § 154.15.

Noblesville Adopted Electrical Code

Some Restrictions

Noblesville Code of Ordinances §§ 154.04(A)(4), 154.15

Building rules of the Indiana Fire Prevention and Building Safety Commission as set out in the following Articles of Title 675 of the Indiana Administrative Code are hereby incorporated by reference in this code ... (4) Article 17 - Electrical Codes: (a) Indiana Electrical Code (b) Safety Code for Health Care Facilities ... A permit shall be obtained before beginning construction, alteration, r...

Plumbing Permits

The City of Noblesville incorporates the Indiana Plumbing Code under Article 16 of Title 675 of the Indiana Administrative Code by reference into its Building Code, per Noblesville Code of Ordinances § 154.04(A)(3), and requires a permit before plumbing work begins under § 154.15.

Noblesville Adopted Plumbing Code

Some Restrictions

Noblesville Code of Ordinances §§ 154.04(A)(3), 154.15

Building rules of the Indiana Fire Prevention and Building Safety Commission as set out in the following Articles of Title 675 of the Indiana Administrative Code are hereby incorporated by reference in this code and shall include later amendments to those Articles as the same are published in the Indiana Register or the Indiana Administrative Code with effective dates as fixed therein: ... (3) ...

Building Inspections

After a building permit issues, the City of Noblesville's Director of Planning must inspect work for code compliance, with the Fire Chief assisting on fire suppression and alarm systems, per Noblesville Code of Ordinances § 154.32, before a certificate of occupancy can be issued under § 154.31.

Noblesville Building Inspection Process

Some Restrictions

Noblesville Code of Ordinances § 154.32

(A) After the issuance of any building permit, the Director of Planning shall make, or shall cause to be made, inspections of the work being done as are necessary to insure full compliance with the provisions of this chapter and the terms of the permit. Reinspections of work found to be incomplete or not ready for inspection are subject to assessment of reinspection fees as prescribed in Ordina...