Key Facts

Dedicated ordinance
None
Zones
M-P, M-1, M-2 industrial
Use type
Industrial-Light or Office-Professional
Permit
Planning Commission Site Development Review
Moratorium
None adopted

Summary

Dublin has no data-center ordinance and no data-center use type. A server building is classified as Industrial-Light in the M-P, M-1, and M-2 districts, or as Office - Professional/Administrative, a definition that names data processing outright.

Use types permitted in the M-P zoning district. Laboratory, Office - Contractor's, Office - Professional/Administrative, Industrial - Light, Printing and Publishing, Research and Development Laboratory, Storage of Petroleum Products for On-Site Use, and Warehousing and Distribution; similar and related uses, temporary uses, and conditional uses.

Source: Dublin Municipal Code Title 8 (Zoning Ordinance) and Chapter 5.28 (Noise)View official code

Full Breakdown

Dublin's Land Use Matrix, Municipal Code Section 8.12.050, lists no data center. Community Development classifies a server farm as Industrial-Light, permitted in the M-P Industrial Park, M-1 Light Industrial, and M-2 Heavy Industrial districts, or as Office - Professional/Administrative, permitted in M-P and M-1, whose Chapter 8.08 definition covers data processing and computer and internet programming and services. In the M-P district every permitted use operates entirely inside a building. Section 8.104.040 sends all new principal structures to the Planning Commission for Site Development Review at a public hearing, a discretionary action that triggers CEQA review.

Violations & Fines

Building without Site Development Review, or operating outside an industrial district, violates the Zoning Ordinance and is enforced by Community Development through stop-work orders, permit revocation, and code enforcement citations.

Frequently Asked Questions

Where can a data center be built in Dublin, CA?
In the M-P Industrial Park, M-1 Light Industrial, and M-2 Heavy Industrial zoning districts, as an Industrial-Light or Office - Professional/Administrative use under the Land Use Matrix in Municipal Code Section 8.12.050.
Does Dublin require a special permit for a data center?
No conditional use permit is tied to data centers. Every new principal structure needs Site Development Review approved by the Planning Commission at a public hearing under Section 8.104.040, which carries CEQA review.
Dublin has no data-center rules. Who do I ask for them?
The City Council sets policy and the Planning Commission hears Site Development Review cases. Start at the City Council page, https://www.dublin.ca.gov/71/Mayor-City-Council, or the Zoning page, https://www.dublin.ca.gov/1627/Zoning.

Sources & Official References

Other rules in Dublin

All Dublin rules

California rules heatmap·Compare Dublin to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Dublin, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Alameda County handle data center zoning & siting.

Fremont, CA
Light Restrictions
San Leandro, CA
Some Restrictions
Livermore, CA
Few Restrictions
Oakland, CA
Few Restrictions
Hayward, CA
Significant Restrictions