Key Facts

Trigger
Any excavation, earth-moving, or site development
Standard applied
Article 4, Cook County Watershed Management Ordinance
Required document
Erosion and sedimentation control plan, Appendix B 2.01
Enforcing office
Village Engineer, Village of Palatine
Permit trigger
Watershed management permit under WMO Section 201
Penalty
Stop-work order (Sec. 8-207); fines under Sec. 8-208

Summary

In the Village of Palatine, Appendix A Section 4.12 subjects all excavation, earth-moving, and site development to the Erosion and Sedimentation Control Ordinance in the subdivision regulations, and Appendix B Section 6.09 requires any development needing a Cook County watershed-management permit to meet Article 4 of the Cook County Watershed Management Ordinance. The Village Engineer reviews the plan through the site-development permit process before construction starts.

4.12. - Erosion and sedimentation control ordinance. All excavation, movement of earth, site development, and execution of an erosion and sedimentation control plan shall be subject to the rules and regulations of the "Erosion and Sedimentation Control Ordinance" found in the Village subdivision regulations. ... 6.09. - Erosion and sedimentation control.(a)Any development or redevelopment requiring a watershed management permit as specified in Section 201 of the Cook County Watershed Management Ordinance shall comply with the requirements of Article 4 of the Cook County Watershed Management Ordinance.

Full Breakdown

The Village folded its erosion-control standard into the regional Cook County Watershed Management Ordinance rather than write numeric limits of its own. Appendix B Section 6.09(a) states that development needing a watershed management permit under Section 201 of the county ordinance must comply with Article 4 of that ordinance, the reservoir of the numeric erosion-and-sediment control standards developers actually build to. Appendix A Section 4.12 broadens the trigger: any excavation, earth-moving, or site development in the village, not only projects needing a county permit, is made subject to the rules and regulations of the Erosion and Sedimentation Control Ordinance found in the Village subdivision regulations, the same Article 4 standard folded back into Appendix B.

Appendix B Section 2.01 defines the paperwork required: an erosion and sedimentation control plan is the site-development document listing every erosion and sediment control measure needed to protect the site throughout all phases of construction, and the code separately defines erosion control practice and erosion and sediment control practice as the physical measures that stabilize soil and intercept runoff. Compliance is checked at the same point other site-development plans are reviewed: Appendix B Article VIII requires the developer's design engineer to be on-site during construction and to notify the Village Engineering Department at least 48 hours before any underground or surface work begins.

Chapter 8's general enforcement tools apply once a permit issues: Section 8-207 lets the Village Manager issue a stop-work order for departing from any ordinance or code of the village, covering a site that fails to run its erosion-control plan, with continued noncompliance escalating to the fine schedule under Section 8-208.

Violations & Fines

A stop-work order under Section 8-207 halts all site work until the erosion and sedimentation control plan required by Appendix B Section 6.09 and Section 2.01 is brought into compliance. Continued noncompliance is punishable under Section 8-208's general village fine schedule, with each day of continuing violation treated as a separate offense. Projects that also need a Cook County watershed-management permit face parallel enforcement under Article 4 of the county's Watershed Management Ordinance, since the permit is conditioned on that compliance.

Frequently Asked Questions

Does Palatine have its own numeric erosion-control standards?
No. Appendix B Section 6.09(a) of the Village Code sends any development needing a watershed-management permit straight to Article 4 of the Cook County Watershed Management Ordinance, and Appendix A Section 4.12 applies that same county standard to all excavation, earth-moving, and site development inside the Village of Palatine, rather than setting the Village's own numeric limits.
What has to be submitted before grading starts?
Appendix B Section 2.01 defines an erosion and sedimentation control plan as the site-development document that must show every erosion and sediment control measure needed to protect the property throughout all phases of construction, reviewed alongside the rest of the final site plan before a Village permit issues.
What happens if a contractor skips the plan?
The Village Manager or a designee can issue a stop-work order under Section 8-207 for departing from any ordinance or code of the village, which halts the project until the erosion-control plan is corrected. Repeated noncompliance is fined under Section 8-208's village fine schedule, with each day counted as a separate offense.

Sources & Official References

Other rules in Palatine

All Palatine rules

Compare Palatine to another location·View the Illinois environmental rules overview

Get notified when Erosion Control in Palatine, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Cook County handle erosion control.

Skokie, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Chicago, IL
Some Restrictions
Evanston, IL
Some Restrictions
Tinley Park, IL
Some Restrictions
Arlington Heights, IL
Some Restrictions
Schaumburg, IL
Some Restrictions