Palatine, IL Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger
- Any excavation, earth-moving, or site development
- Standard applied
- Article 4, Cook County Watershed Management Ordinance
- Required document
- Erosion and sedimentation control plan, Appendix B 2.01
- Enforcing office
- Village Engineer, Village of Palatine
- Permit trigger
- Watershed management permit under WMO Section 201
- Penalty
- Stop-work order (Sec. 8-207); fines under Sec. 8-208
Summary
In the Village of Palatine, Appendix A Section 4.12 subjects all excavation, earth-moving, and site development to the Erosion and Sedimentation Control Ordinance in the subdivision regulations, and Appendix B Section 6.09 requires any development needing a Cook County watershed-management permit to meet Article 4 of the Cook County Watershed Management Ordinance. The Village Engineer reviews the plan through the site-development permit process before construction starts.
4.12. - Erosion and sedimentation control ordinance. All excavation, movement of earth, site development, and execution of an erosion and sedimentation control plan shall be subject to the rules and regulations of the "Erosion and Sedimentation Control Ordinance" found in the Village subdivision regulations. ... 6.09. - Erosion and sedimentation control.(a)Any development or redevelopment requiring a watershed management permit as specified in Section 201 of the Cook County Watershed Management Ordinance shall comply with the requirements of Article 4 of the Cook County Watershed Management Ordinance.
Full Breakdown
The Village folded its erosion-control standard into the regional Cook County Watershed Management Ordinance rather than write numeric limits of its own. Appendix B Section 6.09(a) states that development needing a watershed management permit under Section 201 of the county ordinance must comply with Article 4 of that ordinance, the reservoir of the numeric erosion-and-sediment control standards developers actually build to. Appendix A Section 4.12 broadens the trigger: any excavation, earth-moving, or site development in the village, not only projects needing a county permit, is made subject to the rules and regulations of the Erosion and Sedimentation Control Ordinance found in the Village subdivision regulations, the same Article 4 standard folded back into Appendix B.
Appendix B Section 2.01 defines the paperwork required: an erosion and sedimentation control plan is the site-development document listing every erosion and sediment control measure needed to protect the site throughout all phases of construction, and the code separately defines erosion control practice and erosion and sediment control practice as the physical measures that stabilize soil and intercept runoff. Compliance is checked at the same point other site-development plans are reviewed: Appendix B Article VIII requires the developer's design engineer to be on-site during construction and to notify the Village Engineering Department at least 48 hours before any underground or surface work begins.
Chapter 8's general enforcement tools apply once a permit issues: Section 8-207 lets the Village Manager issue a stop-work order for departing from any ordinance or code of the village, covering a site that fails to run its erosion-control plan, with continued noncompliance escalating to the fine schedule under Section 8-208.
Violations & Fines
A stop-work order under Section 8-207 halts all site work until the erosion and sedimentation control plan required by Appendix B Section 6.09 and Section 2.01 is brought into compliance. Continued noncompliance is punishable under Section 8-208's general village fine schedule, with each day of continuing violation treated as a separate offense. Projects that also need a Cook County watershed-management permit face parallel enforcement under Article 4 of the county's Watershed Management Ordinance, since the permit is conditioned on that compliance.
Frequently Asked Questions
Does Palatine have its own numeric erosion-control standards?
What has to be submitted before grading starts?
What happens if a contractor skips the plan?
Sources & Official References
Other rules in Palatine
Compare Palatine to another location·View the Illinois environmental rules overview