Yuma, AZ Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger
1 acre disturbed (0.5 acre city linear projects)
SWPPP inspection fee
$177 first 10 acres, +$19/5 acres
SWPPP plan review fee
$168 first 10 acres, +$28/5 acres
Cut/fill slope limit
No steeper than 4:1
Stabilization deadline
Within 14 days of clearing/inactivity
Max penalty
$1,000 fine and/or 10 days jail, per day

Summary

Yuma requires a Stormwater Pollution Prevention Plan with an erosion and sediment control plan for any site disturbing one acre or more (half an acre for city linear projects) before a permit issues. City Code Chapter 156 sets design standards, inspection triggers and a class 1 misdemeanor penalty for violations.

The City shall not grant any permit for site development or improvement activity that would fall under this chapter without first having reviewed and approved the applicant's SWPPP and ensured that ADEQ has granted the applicant an AZPDES CGP permit coverage... Cut and fill slopes shall be no greater than 4:1, except as approved by the City Engineer... Soil stabilization shall be completed within 14 days of clearing or inactivity in construction... Any person, firm or corporation violating any of the provisions of this chapter shall be guilty of a class 1 misdemeanor, and upon conviction thereof shall be punished by a fine not to exceed $1,000 or by imprisonment for not more than ten days or both fine and imprisonment.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-74: Current through May 20, 2026).

Full Breakdown

Chapter 156 of the Yuma City Code applies to any development or construction disturbing one acre or more on public or private projects, or one-half acre or more on City-owned linear projects (§ 156-02). Before the City issues a building or grading permit, the applicant must submit a SWPPP containing an Erosion and Sediment Control Plan (ESCP) for review, and ADEQ must have granted AZPDES Construction General Permit coverage (§ 156-04(A)). Emergency work and existing permitted agricultural or nursery operations are exempt from the SWPPP requirement (§ 156-04(B)).

Fees run $177 for SWPPP inspection and $168 for plan review for the first ten acres, plus $19 and $28 respectively for each additional five acres, adjusted every July 1 by the West Urban CPI (§ 156-04(E)). The City Engineer must act on an application within 30 calendar days or the applicant may treat it as approved (§ 156-05(B)). Design requirements cap cut and fill slopes at 4:1 absent City Engineer approval, require soil stabilization within 14 days of clearing or a halt in construction, require reseeding or a non-vegetative fix if vegetative cover has not established within three weeks, and cap allowable soil loss at five tons per acre per year using RUSLE or MUSLE calculations (§ 156-07(A), (E)(1)-(2), (C)(7)).

Phasing is mandatory on any site disturbing more than 40 acres (§ 156-07(D)). Inspectors must be notified at least two working days ahead of the start of construction, completion of rough grading, final grading and final landscaping (§ 156-08(A)). Projects of one acre or larger must post a project information sign at the main entrance (§ 156-10). 4, and unpaved vacant lots, parking lots and roadways not requiring a permit, are exempt (§ 156-11).

Violations & Fines

Constructing, grading, excavating or filling in violation of Chapter 156, or violating permit terms in a way that adversely affects the environment, health, safety or welfare of the neighborhood, lets the City suspend or revoke the building permit (§ 156-09(A)). A separate violation is a class 1 misdemeanor punishable by a fine up to $1,000, up to ten days imprisonment, or both, with each day of continued violation charged as a separate offense (§ 156-09(B)).

Frequently Asked Questions

When does a Yuma construction project need an erosion control permit?
Any project disturbing one acre or more of land, or one-half acre or more for a City-owned linear project like a road or utility line, must submit a SWPPP with an erosion and sediment control plan under City Code § 156-02 before the City will issue a building or grading permit.
How much does Yuma charge for erosion control review?
Under § 156-04(E), SWPPP plan review costs $168 for the first ten acres plus $28 for each additional five acres, and inspection costs $177 for the first ten acres plus $19 for each additional five acres, with fees adjusted every July 1 by the West Urban CPI.
What happens if a Yuma site does not control erosion properly?
The City Engineer can suspend or revoke the building permit under § 156-09(A), and separately, any person violating Chapter 156 is guilty of a class 1 misdemeanor punishable by a fine up to $1,000 and up to ten days in jail, with each day counted as a separate violation under § 156-09(B).
Is farmland exempt from Yuma's erosion control chapter?
Yes. Section 156-11 exempts normal farm and agricultural practices conducted under A.R.S. §§ 49-457 and 49-504.4, along with open areas, vacant lots, and unpaved parking lots or roadways that do not otherwise require a permit.

Sources & Official References

Other rules in Yuma

All Yuma rules

Compare Yuma to another location·View the Arizona environmental rules overview

Get notified when Erosion Control in Yuma, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.