Yuma, AZ Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Min. residential lot for on-site retention
8,000 sq ft
Max. storage depth
8 inches without waiver
Residential design storm
100-year, 24-hr, 3.85 in rainfall
Commercial/industrial design storm
100-year, 1-hr, 2.25 in rainfall
Retention basin max depth
3.5 ft unless approved deeper
Penalty
Class 1 misdemeanor, up to $1,000

Summary

Every new lot, plot or parcel in Yuma must hold its own storm runoff on-site: Chapter 192 sets a 8,000-square-foot minimum lot size for on-site retention, an 8-inch maximum storage depth, and design storms up to the 100-year event, enforced by the City Engineer before any building permit issues.

(A) Residential. When on-site retention is utilized in residential subdivisions, the following design criteria shall be applicable: (1) Minimum lot size for on-site retention shall be 8,000 square feet. A deed covenant prohibiting alteration of the final site ground elevations shall be required. The minimum design depth of storm water storage on any lot shall not exceed eight inches except as approved by the City Engineer. (2) The lot depth below the back edge of the sidewalk shall be computed using a 100-year storm of 24-hour duration with 3.85 inches of total rainfall. An allowance for evaporation and/or percolation shall not be incorporated into the computations for minimum lot depth. Storage volume shall also be provided for adjacent streets and alleys except for arterial streets. (3) Each lot shall be provided with an earthen berm around the back and sides of each lot. The earthen berm shall be one foot higher than the adjacent final ground elevation of the lot.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-74: Current through May 20, 2026).

Full Breakdown

Yuma City Code Chapter 192 requires the owner or developer of every lot to provide storage for the total runoff generated by the design storm falling on that parcel, using on-site retention, a retention basin, or a combination of both (§ 192-02, § 192-03). The City Engineer can waive the requirement only when runoff can be directed into a storm sewer, channel or natural drainageway with capacity to carry it to an approved disposal site (§ 192-02(A)). 85 inches of rainfall, with no credit for evaporation or percolation.

Each lot must carry an earthen berm one foot higher than the adjacent final grade. 25 inches on-site, and dry wells may drain the surface but cannot count toward required storage volume (§ 192-05(B)). Retention basins in residential subdivisions are capped at three and one-half feet deep unless the City Engineer approves greater depth, which then triggers a mandatory six-foot masonry fence and locked 16-foot gate (§ 192-04(B)). Filling or substantially altering a lot's surface requires written City Engineer approval and an engineer-prepared drainage plan before Development Services will issue a building permit or certificate of occupancy (§ 192-08).

Violations & Fines

Chapters 192 sections 192-04, 192-05, 192-07 and 192-08 each cross-reference the penalty at § 193-99: any person or corporation violating the chapter is guilty of a class 1 misdemeanor, punishable under § 10-99 by a fine of up to $1,000, imprisonment for up to ten days, or both. The Division of Building Safety will not issue a building permit until the City Engineer confirms an approved drainage plan, and will withhold a certificate of occupancy until construction is verified as substantially compliant.

Frequently Asked Questions

Can I skip building a retention basin on my Yuma lot?
Only if the City Engineer approves directing your runoff into an existing storm sewer, channel or natural drainageway with enough capacity to carry it to an approved disposal site under § 192-02(A). Otherwise every lot must retain its own design-storm runoff on-site.
How deep can my yard's stormwater storage be under Yuma's code?
Residential on-site retention is capped at 8 inches of design depth under § 192-05(A)(1) unless the City Engineer approves a deeper design. The lot must also carry a recorded deed covenant barring later changes to the final ground elevations.
Does grading my own lot in Yuma require city approval?
Yes. Section 192-08 requires written City Engineer approval before filling or substantially altering a lot's surface, plus an engineer-prepared drainage plan for most projects, and the Building Safety Division will not issue a building permit or certificate of occupancy without it.

Sources & Official References

Other rules in Yuma

All Yuma rules

Compare Yuma to another location·View the Arizona environmental rules overview

Get notified when Stormwater Management in Yuma, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.