Key Facts
- Freeboard required
- One foot above BFE (the RFE)
- Applies to
- New construction and substantial improvements
- Certification
- Registered engineer or surveyor, verified by building inspector
- AO zone minimum
- Two feet above highest adjacent grade if unspecified
Summary
Yuma requires one foot of freeboard above FEMA's base flood elevation: City Code section 151-04 sets the Regulatory Flood Elevation at BFE plus one foot, and section 151-18 makes new construction and substantial improvements in Special Flood Hazard Areas meet or exceed that elevation.
REGULATORY FLOOD ELEVATION (RFE). An elevation one foot above the BFE. ... (C) Elevation and floodproofing. (1) Residential construction. (a) Residential construction, new or substantial improvement, shall have the lowest floor, including basement, elevated to or above the RFE
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-74: Current through May 20, 2026).
Full Breakdown
City Code section 151-04 defines the Regulatory Flood Elevation (RFE) as an elevation one foot above the Base Flood Elevation (BFE), building in a mandatory one-foot freeboard margin above FEMA's mapped flood elevation. Section 151-18(C)(1) carries that standard into construction: residential new construction and substantial improvements must have the lowest floor, including any basement, elevated to or above the RFE. In an AO Zone, that means the elevation shown on the FIRM panel or, if unspecified, at least two feet above the highest adjacent grade; in an A Zone without a determined BFE, the lowest floor must reach the RFE; in AE and AH zones, the BFE comes from the Flood Insurance Study or FIRM.
A garage attached to a residence with its slab below the RFE must be built to allow floodwater to enter and exit automatically and may be used only for parking, access or storage. Nonresidential structures under section 151-18(C)(2) must either meet the same elevation or be floodproofed below it so the structure is watertight, with walls substantially impermeable to water and structural components able to resist hydrostatic and hydrodynamic loads. Upon completion, a registered professional engineer or surveyor must certify the lowest floor elevation, verified by the city's building inspector, and that certification goes to the Floodplain Administrator.
Section 151-17(I)(5)(n) separately bars new construction, fill or other development in Zone AE unless it is shown the cumulative effect will not raise the BFE by more than one foot anywhere in the city.
Violations & Fines
A structure built without the elevation certificate or other compliance evidence required by this chapter is presumed in violation under the chapter's violation definition. Under section 151-12, engaging in unauthorized development that creates a flood hazard is a Class 2 misdemeanor, with each day of continuation a separate offense, and section 151-13 exposes noncompliant development to abatement as a public nuisance per se.
Frequently Asked Questions
How much freeboard does Yuma require above base flood elevation?
Who certifies that a new building meets Yuma's flood elevation requirement?
What if my lot is in an AO Zone with no depth number on the FIRM?
Sources & Official References
Other rules in Yuma
Compare Yuma to another location·View the Arizona environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.