Rohnert Park, CA Parking Rules: EV Charging (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing chapter
RPMC Chapter 15.34
State mandate
Gov. Code § 65850.7
Denial appeal body
Building Board of Appeals
City-project EVITP minimum
50% of licensed electricians certified
Wiring standard
Article 625, California Electrical Code

Summary

Rohnert Park's Chapter 15.34 gives electric vehicle charging stations an expedited permit review, required by state Government Code Section 65850.7. The building official can deny only on a documented health or safety finding, and city-funded EV projects must use electricians certified through the EV Infrastructure Training Program.

15.34.020 - Purpose. The purpose of this section is to provide an expedited, streamlined permitting process for EVCS as required by California Government Code Section 65850.7. ... 15.34.060 - Permit review and inspection requirements. A.An application that satisfies the information requirements in the checklist provided under Subsection 15.34.050(e) and (f), as determined by the building official, shall be deemed complete. ... D.The building official may deny the building permit if the building official makes a finding based on substantial evidence that the EVCS could have a specific, adverse impact upon the public health and safety, and may require application for an conditional use under Section 17.25.010. ... I.EVCS are subject to inspection in accordance with applicable provisions of the California Building Code. Construction of the EVCS shall remain visible and able to be accessed for inspection until approved.J.If EVCS fails inspection, a subsequent inspection shall be required by the building official.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 51 Update 2).

Full Breakdown

7. EVCS legally established before the chapter's effective date are exempt unless physically modified in a way that materially changes size, type or components and requires new permitting; routine operation and maintenance never triggers a new permit. Installations must meet Article 625 of the California Electrical Code and be treated as a continuous load in electrical load calculations. Applications and supporting documents may be submitted by email, fax, or an online permitting system, with electronic signatures accepted in place of a wet signature, and the city manager or designee implements a standard EV checklist that substantially conforms to the state's Zero-Emission Vehicles in California Community Readiness Guidebook.

060, an application satisfying the checklist is deemed complete, and the building official's review is limited to whether the installation meets local, state and federal health and safety requirements. 010; that denial can be appealed to the building board of appeals. Construction must stay visible and accessible for inspection until approved, and a failed inspection triggers a required follow-up inspection. For projects funded or administered by the city, EV work requires at least one job-site supervisor holding EVITP certification and a licensed electrician on site, with at least fifty percent of the licensed electricians performing the work also EVITP-certified.

Violations & Fines

A denial for specific, adverse health or safety impact routes the applicant to a conditional use permit process under Section 17.25.010, appealable to the building board of appeals rather than fined outright. On city-funded projects, contractors who fail to meet the EVITP-certification and licensing ratios under Section 15.34.070 are out of compliance with the contractor requirements for that work, and must maintain written or electronic records of certified electricians available to the city on request.

Frequently Asked Questions

Can Rohnert Park deny my home EV charger permit?
Only on a finding, based on substantial evidence, that the installation could have a specific, adverse impact on public health and safety. Absent that finding, the building official must review only for health and safety code compliance and approve the permit under Section 15.34.060.
What electrical code applies to EV charging stations?
Installation of the charging station, wiring, bonding, disconnects and overcurrent protection must meet Article 625 of the California Electrical Code, and the equipment is treated as a continuous load in electrical service calculations under Section 15.34.040.
Do city-funded EV charging projects need certified electricians?
Yes. At least one job-site supervisor must hold EVITP certification and be a licensed electrician, and at least fifty percent of the licensed electricians performing the work on each job site must also hold EVITP certification, under Section 15.34.070.

Sources & Official References

Other rules in Rohnert Park

All Rohnert Park rules

California rules heatmap·Compare Rohnert Park to another location·View the California parking rules overview

Get notified when EV Charging in Rohnert Park, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in Sonoma County handle ev charging.

Petaluma, CA
Some Restrictions
Santa Rosa, CA
Some Restrictions