Key Facts

Permit required for
Construct, alter, repair, move or demolish
Minor repair exception
Building inspector approval, no permit needed
Base permit fee
$50 minimum, or $5 per $1,000 of cost
Unpermitted work penalty
Doubled fee plus flat $500 fine
Permit expiration
Six months unused or one year abandoned

Summary

Bossier City requires a building permit before anyone constructs, enlarges, alters, repairs, moves, or demolishes a building or structure, per section 18-38. Section 18-39 backs that with a flat ban on unpermitted work. The building official reviews plans against the adopted Code before issuing the permit, and starting work first doubles the fee under section 18-40.

Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, or construct a sign of any description, or to install or alter fire-extinguishing apparatus, elevators, engines, or to install a steam boiler, furnace, heater, incinerator, or other heat producing apparatus, or other appurtenances, the installation of which is regulated by this Code, or to cause any such work to be done, shall first make application to the building official and obtain the required permit therefor. ... A person, firm or corporation shall not erect, construct, enlarge, alter, repair, move, improve, remove, convert or demolish any building or structure in the applicable jurisdiction, or cause the same to be done, without first obtaining a separate building permit for such building or structure for the building official.

Full Breakdown

Section 18-38(1)(a) of the Bossier City Code requires any owner, authorized agent, or contractor who wants to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect a sign, install fire-extinguishing apparatus or elevators, or install a boiler, furnace, heater, or incinerator regulated by the Code, to first apply to the building official and obtain a permit. Section 18-39(1)(a) states the flip side as a flat prohibition: no person, firm or corporation may erect, construct, enlarge, alter, repair, move, improve, remove, convert, or demolish a building or structure without first obtaining a separate building permit.

Ordinary minor repairs may proceed without a permit only with the building inspector's approval under section 18-38(1)(c). Applications must include a general description of the work, indicate proposed occupancy, and for larger occupancy groups or projects exceeding $125,000.00, plans must be sealed by a Louisiana-registered architect or engineer under section 18-38(3)(b). Section 18-40 sets the fee schedule: a $50.00 minimum for work under $2,000.00 and $5.00 per $1,000.00 above that, with new residential permits at $350.00 plus $0.15 per square foot under roof. Starting work before securing a permit doubles the fee and adds a flat $500.00 penalty under section 18-40(b).

A permit lapses if work has not begun within six months of issuance or is abandoned for a year, though the building official may grant 90-day extensions for cause under section 18-38(5).

Violations & Fines

Building without a permit doubles the regular fee and adds a flat $500.00 penalty under section 18-40(b). Beyond that fee, violating the Code's permit requirement is a misdemeanor under section 18-47, punishable by a fine up to $500.00, up to 60 days imprisonment, or both, with each day of continuing violation a separate offense.

Frequently Asked Questions

When do I need a building permit in Bossier City?
Section 18-38 requires a permit before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building, or before installing regulated equipment like boilers or elevators. Ordinary minor repairs can skip the permit only if the building inspector approves them in advance.
What happens if I start construction before getting a permit?
Section 18-40(b) doubles the normal permit fee and adds a flat $500.00 penalty. You still must bring the work into full compliance with the Code, and the violation itself is a separate misdemeanor under section 18-47.
How long is a Bossier City building permit valid?
A permit is treated as abandoned six months after filing if work has not started, or after one year if work is suspended, under section 18-38(5). The building official may allow one or more 90-day extensions for cause.

Sources & Official References

Other rules in Bossier City

All Bossier City rules

Compare Bossier City to another location·View the Louisiana building safety overview

Get notified when Building Permits in Bossier City, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.