Grand Forks, ND Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

First notice
Work ready for inspection and test
Second notice
Final inspection after fixtures installed
Response time
Inspector must act within 8 working hours
Fixture rule
No fixture until drain/waste/vent test passes
Penalty
Up to $1,000 per day, § 19-0340

Summary

Grand Forks stages plumbing inspection in two required calls: § 19-0328 requires the plumber to notify the plumbing inspector when installation work is ready for test, and again when all fixtures are in and the job is ready for final inspection, and § 19-0332 bars installing any fixture until the drain, waste, and vent system has been tested and found tight.

19-0328. - Plumber or sewer and water contractors to notify plumbing inspector. (1)The plumber or sewer and water contractor shall notify the plumbing inspector whenever the plumbing or sewer and water installation work for which a permit has been issued is ready for inspection and test.(2)After all fixtures have been installed, the plumber shall again notify the plumbing inspector as herein provided that the work is ready for final inspection and no plumbing shall be used until after it shall have been inspected and approved by the plumbing inspector. ... 19-03 ... 32. - When installation of fixtures prohibited. No fixture shall be installed until the drain, waste, and vent system have been tested and found to be tight according to the provisions of this article. ... 19-03 ... 40. - Violations and penalties. Any person, firm, or corporation violating any of the terms or provisions of this article shall be subject to a penalty not to exceed one thousand dollars ($1,000.00). Each day that a violation is permitted to exist shall constitute a separate offense.

Full Breakdown

Section 19-0328 sets the two-notice sequence a plumber or sewer and water contractor must follow: first, "notify the plumbing inspector whenever the plumbing or sewer and water installation work for which a permit has been issued is ready for inspection and test," and second, after fixtures go in, "again notify the plumbing inspector... that the work is ready for final inspection," with the plumbing barred from use "until after it shall have been inspected and approved." Section 19-0329 puts a clock on the city's response: the inspector must act "within a reasonable time, not exceeding eight (8) working hours after receiving such notice," to "make the necessary inspection and supervise such tests." Section 19-0332 locks the sequence in place from the installer's side: "No fixture shall be installed until the drain, waste, and vent system have been tested and found to be tight according to the provisions of this article," and a related section requires all piping to stay uncovered until that test is complete, so concealment cannot outrun inspection.

The plumbing inspector's general duties at § 19-0333, to "see that the provisions of this article are enforced," to "issue permits," and to "make inspections of all new and existing plumbing installations," tie the notice-test-final sequence back to the § 19-0317 permit that starts the process. Every step in this chain sits inside Article 3, so a failure at any stage, an unreported test, an installed fixture ahead of testing, or a skipped final inspection, is treated the same way under the article's closing violations section.

Violations & Fines

Article 3's violations clause, § 19-0340, sets a penalty of up to $1,000 for violating "any of the terms or provisions of this article," including the notice, testing, and final-inspection sequence in §§ 19-0328, 19-0329, and 19-0332, with "each day that a violation is permitted to exist" counted as "a separate offense" until the work is properly inspected and approved.

Frequently Asked Questions

How many times must a plumber notify the inspector in Grand Forks?
Twice. Section 19-0328 requires the plumber to notify the inspector when the work is ready for the initial inspection and test, then to notify again after all fixtures are installed so the inspector can perform a final inspection before the plumbing may be used.
How fast must the city respond to a plumbing inspection request?
Eight working hours at most. Section 19-0329 requires the plumbing inspector to make the necessary inspection and supervise the required tests "within a reasonable time, not exceeding eight (8) working hours after receiving such notice" from the plumber or contractor.
Can a plumber install fixtures before the system is tested?
No. Section 19-0332 bars installing any fixture "until the drain, waste, and vent system have been tested and found to be tight," and a companion section requires piping to stay uncovered until that test is complete, so concealment cannot outrun inspection.

Sources & Official References

Other rules in Grand Forks

All Grand Forks rules

Compare Grand Forks to another location·View the North Dakota building safety overview

Get notified when Building Inspections in Grand Forks, ND changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.