Key Facts

Advance notice required
24 hours before work starts
Notice goes to
Division of Building and Housing
CO condition
Improvements "inspected and found to be satisfactory"
First-offense fine (Ch. 87)
$250 to $5,000
Temporary CO validity
3 months, one 3-month extension
Grading inspections
Required at each project stage

Summary

Permit holders in Huntington must give the town 24 hours' advance notice before starting work, and a certificate of occupancy will not issue until the Building Inspector confirms every on-site improvement has actually been inspected and found satisfactory. Both steps run through the Department of Engineering Services.

I. The Department of Engineering Services, Division of Building and Housing shall be given at least twenty-four (24) hours' advance notice of the commencement of work under a permit. Failure to provide such notice shall be a violation of this article. [§ 87-19] ... The certificate shall be issued when the Building Inspector determines that the completed building, telecommunications facility or structure complies with the provisions of all applicable laws and the required on-site improvements have been completed, inspected and found to be satisfactory. [§ 87-28(A)]

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4940543; v75 updated 2026-06-09; through 06-09-2026).

Full Breakdown

Section 87-19(I) of the Building Construction chapter requires that the Department of Engineering Services, Division of Building and Housing, receive at least twenty-four hours' advance notice before work commences under a permit; failing to give that notice is itself a violation of the article. The same section lets the Department post stop-work orders and revoke the permit if the work performed strays from the approved plans, specifications or conditions (§ 87-19(C), (E), (F), (H)), and gives permit holders ten days after a sale to reassign a permit to a new owner.

On the closing end of the process, § 87-28(A) ties issuance of the certificate of occupancy or certificate of permitted use directly to inspection: the certificate is issued only when the Building Inspector determines the completed building or structure complies with all applicable laws and that the required on-site improvements have been completed, inspected and found to be satisfactory. Section 87-29 adds further conditions before any certificate can be released, including that any required fire hydrants, water mains and appurtenant facilities be installed and in good working order, and that all Town Board, Zoning Board of Appeals or Planning Board conditions be satisfied.

A temporary certificate of occupancy may issue under § 87-26 for a completed portion of the work, valid up to three months with one three-month extension available for good cause. For grading-permit work specifically, § 87-98 requires inspection at each stage, including before covering any portion of the work and upon completion of site preparation, excavation and regrading, with the permit holder responsible for scheduling those inspections.

Violations & Fines

Section 87-45(A) sets the general Chapter 87 penalty: $250 to $5,000 for a first offense, $1,000 to $10,000 for a second offense within five years, and $1,500 to $15,000 for a third or later offense within five years, with each day a violation continues counted as a separate offense. Failing to give the required 24-hour inspection notice is a violation of Article III, and work found to deviate from the approved plans or permit can trigger a stop-work order and permit revocation under § 87-19 and § 87-44 on top of the fine.

Frequently Asked Questions

How much notice do I have to give Huntington before an inspection?
Section 87-19(I) requires at least 24 hours' advance notice to the Department of Engineering Services, Division of Building and Housing, before commencing work under a building permit. Skipping this notice is itself a code violation.
What has to happen before I get a certificate of occupancy?
Under § 87-28(A), the Building Inspector must determine the completed building complies with all applicable laws and that the required on-site improvements have been completed, inspected and found satisfactory before a certificate of occupancy or permitted use can be issued.
Can I get a certificate of occupancy for part of a project before it's all finished?
Yes. Section 87-26 allows the Director of Engineering Services to issue a temporary certificate of occupancy for a completed portion that can be safely occupied, valid up to three months with one additional three-month extension for good cause.
What happens if my work doesn't match the approved plans?
Section 87-19(C) makes any deviation from the approved plans, specifications or permit a violation, and the Town can issue a stop-work order and revoke the permit under §§ 87-19 and 87-44, on top of the fines set in § 87-45.

Sources & Official References

Other rules in Huntington

All Huntington rules

New York rules heatmap·Compare Huntington to another location·View the New York building safety overview

Get notified when Building Inspections in Huntington, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Suffolk County handle building inspections.

Islip, NY
Some Restrictions
Babylon, NY
Some Restrictions