Mount Prospect, IL Building Safety: Building Inspections (2026)
Key Facts
- Who requests
- The contractor, in writing or by telephone
- Stages listed
- 11, footing through final completion
- Missed inspection
- Contractor must uncover all closed work
- Entry authority
- Director and inspectors, at any reasonable hour, with identification
- Reinspection fee
- Paid by the general contractor on the permit
- Spot survey
- Due immediately after foundation and footings are installed
Summary
In the Village of Mount Prospect, Village Code § 21.215 makes it unlawful to keep building after a permit issues unless the contractor applies in writing to the Department of Community Development for inspection at each of 11 listed stages, from the footing pour to the final inspection before the certificate of occupancy.
A. It shall be unlawful to proceed with the construction of any building for which a permit is issued unless the contractor makes written application to the department of community development for inspections in each of the following instances: 1. When ready for footing to be poured; 2. When foundation is ready to be poured; 3. Before foundation is backfilled and drain tile is covered; 4. When sewer and/or water installation is ready; 5. When stack is installed; 6. When rough plumbing is installed; 7. When electrical piping and wiring have been installed; 8. When rough framing is completed; 9. When insulation is installed; 10. When ready to pour basement floor; 11. When all work is completed and prior to the issuance of the certificate of occupancy pursuant to section 21.218 of this article. ... ... C. Whenever the contractor or builder proceeds with work without requesting an inspection as above set forth, he shall be required to uncover all closed work to enable proper inspection of work performed, and failure of contractor to procure inspection as above provided, will subject him to the penalties provided for in this code.
Full Breakdown
The contractor, not the Village, starts every inspection. Section 21.215(A) lists the stages: when ready for footing to be poured, when the foundation is ready to be poured, before the foundation is backfilled and the drain tile is covered, when sewer or water installation is ready, when the stack is installed, when rough plumbing is installed, when electrical piping and wiring have been installed, when rough framing is completed, when insulation is installed, when ready to pour the basement floor, and when all work is completed and before the certificate of occupancy. Requests go in by telephone or on blanks supplied by the department (subsection B).
A related step comes early. Under § 21.213(B), immediately after the foundation and footings are installed, the permit holder must submit a spot survey bearing the certificate of an Illinois licensed land surveyor, showing the exact location of the foundation and footings against the lot lines and the elevations of the top of foundation. Construction work cannot proceed until the director approves it. The exception covers additions to existing single-family buildings where a survey was presented before the permit issued.
Inspectors have the right to enter. Under § 21.216, the director and authorized inspectors, on presenting proper identification, can enter any building, structure or premises, occupied, completed or under construction, at any reasonable hour when needed to perform a duty under the building code. Interfering with or hindering them is unlawful and is fined under appendix A, division III.
Stop orders back the schedule up. Under § 21.217, the director serves written notice of a violation and, if the work or condition continues, issues a stop order on all construction. The director can stop work without notice when public health and safety are endangered or when work began without permits. Stop order signs can be removed only by the director or the inspectors. A reinspection for the same deficiency, under § 21.317, is charged to the general contractor listed on the permit, at the fee in appendix A, division II. Under § 21.218, no building is occupied until a certificate of occupancy is granted under § 15.703.
Violations & Fines
Skipping a required inspection forces the contractor to uncover all closed work so it can be inspected, and § 21.215(C) subjects the contractor to the penalties in the code. Under § 21.403, each violation is fined at the appendix A, division III amount, and every day is a separate offense. Removing a stop order sign or working around a posted notice exposes the contractor and workers to the same penalties.
Frequently Asked Questions
Which inspections does a Mount Prospect contractor have to request?
How do I request an inspection?
What if work was covered before it was inspected?
Who pays for a reinspection?
Is a survey required during construction of a new building?
Sources & Official References
Other rules in Mount Prospect
Compare Mount Prospect to another location·View the Illinois building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Cook County handle building inspections.