Key Facts

Adopted code
2020 National Electrical Code, with local amendments
Interior wire
Aluminum wire prohibited; solid or stranded copper only
Permit
Required before any change in electrical piping
Permit fee
Set in appendix A, division II
Inspection
When electrical piping and wiring have been installed
Contractor license
Proof of Illinois municipal electrical contractor license

Summary

In the Village of Mount Prospect, Village Code § 21.107 adopts the 2020 National Electrical Code with local amendments, including a ban on aluminum wire inside the structure. Electrical piping changes need a permit from the Department of Community Development under § 21.203, and § 21.304 sends the permit fee to appendix A, division II.

The 2020 edition of the National Electrical Code and appendices, promulgated by the National Fire Protection Association, is hereby adopted in its entirety, except such portions thereof as may be expressly deleted, modified or amended by this section. ... ... 1. Aluminum wire is strictly prohibited inside the structure. All conductors shall be of solid or stranded copper on the interior of the structure. 2 ... 1.304: ... ELECTRICAL PERMITS: ... The permit fee to be charged for electrical installation and alteration is set forth in appendix A, division II of this code.

Full Breakdown

Section 21.107 adopts the 2020 National Electrical Code and appendices in their entirety, except portions the section expressly deletes, modifies or amends, and the local exceptions control wherever they conflict with the NEC. Aluminum wire is strictly prohibited inside the structure, and all interior conductors must be solid or stranded copper. Aluminum or copper-clad aluminum service entrance conductors are allowed under the NEC only if installed by a qualified electrician to the manufacturer's torque specifications, regularly inspected, and used with a panel and meter socket labeled and listed for them.

The local amendments run to detail. Nonmetallic-sheathed cable, service-entrance cable, electrical nonmetallic tubing, concealed knob and tube and several other wiring methods are prohibited unless the code official specifically approves them. Bracket boxes must be screwed, not nailed, in new work unless space limitations make it impractical, and lay-in fixtures in grid ceilings need at least two (2) independent hanger rods. Furnaces and central air units, through-wall heating or air conditioning units, built-in microwave ovens, and sump and ejector pumps each need a dedicated branch circuit. In commercial work, panels over two hundred (200) amp take bolt-in breakers only, and each parking lot or street lighting pole gets a grounding electrode at least eight feet (8') long and one-half inch (1/2") in diameter.

The permit itself comes from § 21.203(A)(1), which makes it unlawful to change electrical piping before the proper permits are obtained from the Department of Community Development. Section 21.204(A) requires other permits, electrical included, to be approved before a building permit issues. Section 21.304 sets the electrical installation and alteration fee in appendix A, division II. Electrical piping and wiring get an inspection under § 21.215(A)(7) when installed.

Electricians face a licensing check under § 11.601(B): an electrical contractor must submit proof of a current electrical contractor license issued by an Illinois municipality, approved by the building official, that administers a competency exam based on the National Electrical Code or the City of Chicago Electrical Code.

Violations & Fines

Under § 21.403, each violation of Chapter 21 is fined at the amount in appendix A, division III, and each day is a separate offense. Electrical work started without a permit has the specified permit fee doubled under § 21.403C, and the director can issue a stop order without notice under § 21.217(B). A contractor who skips the electrical rough-in inspection must uncover the closed work under § 21.215(C).

Frequently Asked Questions

Which National Electrical Code edition applies in Mount Prospect?
The 2020 edition. Section 21.107 adopts the 2020 National Electrical Code and appendices in their entirety, except portions expressly deleted, modified or amended by the section, and it also adopts sections 210.52(G)(1)(a)(1) and 210.52(G)(1)(a)(2) as outlined in § 21.230. The local exceptions control where they conflict with the NEC.
Can I use aluminum wiring inside a house?
No. Section 21.107(A)(1) says aluminum wire is strictly prohibited inside the structure and that all conductors must be solid or stranded copper on the interior. The one allowance is for aluminum or copper-clad aluminum service entrance conductors, which need a qualified electrician, torque specifications, regular inspection and a labeled, listed panel and meter socket.
Do I need a permit for electrical work?
Yes. Section 21.203(A)(1) makes it unlawful to make any change in electrical piping before the proper permits are obtained from the Department of Community Development. The fee for electrical installation and alteration is set in appendix A, division II under § 21.304, and the work is inspected once the piping and wiring are installed.
Is Romex allowed under the Mount Prospect code?
Only with approval. Section 21.107(A)(6)(e) prohibits nonmetallic-sheathed cable, along with service-entrance cable and several other wiring methods, unless the code official specifically approves it. Ask the Department of Community Development for that approval before pulling cable, because the amendment overrides the NEC.
Who can do electrical work as a contractor?
An electrical contractor must submit proof of a current electrical contractor license issued by a municipality within Illinois, approved by the building official, that administers a competency exam based on the National Electrical Code or the City of Chicago Electrical Code. Section 11.601(B) adds this to the contractor license requirements.

Sources & Official References

Other rules in Mount Prospect

All Mount Prospect rules

Compare Mount Prospect to another location·View the Illinois building safety overview

Get notified when Electrical Permits in Mount Prospect, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Cook County handle electrical permits.

Arlington Heights, IL
Some Restrictions
Chicago, IL
Some Restrictions
Evanston, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Oak Park, IL
Some Restrictions
Schaumburg, IL
Some Restrictions
Skokie, IL
Some Restrictions
Tinley Park, IL
Some Restrictions