Construction hours in Mount Prospect, IL, sometimes called construction noise rules or contractor work-hour ordinances, set when contractors can run power tools, hammers, and heavy equipment.

Key Facts

Prohibited hours
Seven o'clock (7:00) P.M. to seven o'clock (7:00) A.M.
Covered activity
Power tools, excavation, demolition, equipment moves, material loading
Emergency permit
From the village manager, up to three (3) days
Liability
Worker, contractor, permittee, owner and occupier, jointly and severally
Residential districts
R-X, R-1, R-A, R-2, R-3 and R-4
Exemptions there
Snow removal, municipal operations, bona fide emergency home repairs

Summary

In the Village of Mount Prospect, the Night Construction section, Village Code § 21.226, covers all locations between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M. and treats those as the prohibited hours for construction related activity. Section 23.1403.1 bars power tools and construction equipment in residential districts in the same window.

A. All locations between seven o'clock (7:00) P.M. to seven o'clock (7:00) A.M.: For purposes of this subsection "construction related activity" shall mean any use of percussion or power tools, excavation, demolition and the moving of powered construction equipment and the loading or unloading of construction material or equipment. If work within the prohibited hours is necessary to protect health, safety or property, an owner may apply to the village manager for an emergency work permit. Emergency work permits may be issued for the minimum time necessary to complete the emergency work up to a maximum of three (3) days. ... It shall be unlawful between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M., within the R-X, R-1, R-A, R-2, R-3 or R-4 residential districts, to do any of the following acts: ... ... D. Operate any percussion tools, power tools, power lawn tools or power construction equipment.

Full Breakdown

Section 21.226 defines construction related activity as any use of percussion or power tools, excavation, demolition, the moving of powered construction equipment, and the loading or unloading of construction material or equipment. The rule applies at all locations, and the prohibited hours run from seven o'clock (7:00) P.M. to seven o'clock (7:00) A.M. The only relief is an emergency work permit. If work in those hours is necessary to protect health, safety or property, the owner applies to the village manager, who can issue a permit for the minimum time needed to finish the emergency work, up to a maximum of three (3) days. The permit can be renewed for periods of up to three (3) days while the emergency continues.

Liability is spread wide. The person actually committing the violation, the general contractor, the permittee, the property owner and the property occupier are jointly and severally liable for any violation of the section.

Residential districts get a second rule in § 23.1403.1. Between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M., within the R-X, R-1, R-A, R-2, R-3 and R-4 districts, it is unlawful to operate any percussion tools, power tools, power lawn tools or power construction equipment. The same section bars driving a commercial vehicle to an address to load or unload it, loading or unloading a commercial vehicle, and running the engine or refrigeration unit of a parked commercial vehicle, with an exception for residential moving vans. The prohibitions do not apply to snow removal, municipal operations or bona fide emergency home repairs.

Noise from these hours also counts under the nuisance article. Section 23.1403(H) makes offensive noise that disturbs the peace of the neighborhood a nuisance and lists § 21.226 and § 23.1403.1 among the provisions it includes. Item I of the same section makes it a nuisance to leave dirt, mud, gravel or rock on public streets after the completion of each day of construction work.

Violations & Fines

Section 21.403 fines each violation of Chapter 21, including § 21.226, at the appendix A, division III amount, and every day is a separate offense. Because night noise is listed in § 23.1403(H), the nuisance abatement procedure in § 23.1404 also applies, and a nuisance not abated within thirty (30) days, or the shorter time in an order, carries a daily nuisance fee under § 23.1406 in the amount set in appendix A, division II.

Frequently Asked Questions

What hours is construction barred in Mount Prospect?
Section 21.226 covers all locations between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M. and defines construction related activity as percussion or power tools, excavation, demolition, moving powered construction equipment, and loading or unloading construction material or equipment. Emergency work permits are the only stated exception.
Can I get a permit to work at night?
Only for an emergency. If work in the prohibited hours is necessary to protect health, safety or property, the owner applies to the village manager for an emergency work permit, issued for the minimum time necessary and no longer than three (3) days. It can be renewed for periods up to three (3) days while the emergency continues.
Who is liable for a night construction violation?
Several parties at once. Section 21.226 makes the person actually committing the violation, the general contractor, the permittee, the property owner and the property occupier jointly and severally liable for any violation of the section, so a homeowner cannot point only at the contractor.
Do residential districts have a separate rule?
Yes. Section 23.1403.1 makes it unlawful, between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M. in the R-X, R-1, R-A, R-2, R-3 and R-4 districts, to operate percussion tools, power tools, power lawn tools or power construction equipment. Snow removal, municipal operations and bona fide emergency home repairs are exempt.
Does the night rule cover deliveries to a job site?
Yes. Section 21.226 includes the loading or unloading of construction material or equipment in its definition of construction related activity. In residential districts, § 23.1403.1 also bars loading or unloading a commercial vehicle between seven o'clock (7:00) P.M. and seven o'clock (7:00) A.M., except residential moving vans.

Sources & Official References

Other rules in Mount Prospect

All Mount Prospect rules

How Mount Prospect compares: Cities with the Strictest Construction Hours·Compare Mount Prospect to another location·View the Illinois noise ordinances overview

Get notified when Construction Hours in Mount Prospect, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Construction Hours in Nearby Cities

How other cities in Cook County handle construction hours.

Arlington Heights, IL
Some Restrictions
Chicago, IL
Some Restrictions
Des Plaines, IL
Some Restrictions
Evanston, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Schaumburg, IL
Some Restrictions
Skokie, IL
Some Restrictions
Tinley Park, IL
Some Restrictions