Mount Prospect, IL Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Issuing office
Department of community development
Start deadline
Within 60 days after the permit is issued
Completion deadline
One year; village manager can extend to 2 years at most
Work without a permit
Permit fee doubled under section 21.403C
Adopted plumbing code
Illinois State Plumbing Code, 77 Ill. Adm. Code 890
Fee schedule
Appendix A, division II of the Village Code

Summary

In the Village of Mount Prospect, Illinois, nobody can make any change in plumbing before the proper permits are obtained from the department of community development. Construction must start within sixty days of issuance, and work begun without a permit doubles the permit fee under section 21.403C of the Village Code.

A. Types Of Work Requiring A Building Permit: 1. It shall be unlawful to proceed with erection, construction, alteration, repair, removal, demolition or excavation for any building or structure or make any change in plumbing, heating or electrical piping, air conditioning or appurtenance; or to alter the grade of any lot or to occupy a portion of a street or alley before the proper permits for such work or occupancy have been obtained from the department of community development. Any person beginning work prior to obtaining a permit for such work shall be subject to the penalty as indicated in subsection 21.403C of this chapter. ... ... B. Issuance Of Permit: Building permits are issued with the understanding that construction shall start within sixty (60) days after issuance of the permit and to be carried to completion within one year.

Full Breakdown

Section 21.203 of the Mount Prospect Village Code makes it unlawful to proceed with erection, construction, alteration, repair, removal, demolition or excavation, or to make any change in plumbing, heating or electrical piping, air conditioning or appurtenance, before the proper permits have been obtained from the department of community development. Plumbing work starts with a permit application to that department.

Section 21.203B sets the clock on every building permit. Construction has to start within sixty (60) days after issuance and be carried to completion within one year. If operations are not started within sixty days, or if work stops for a period of thirty (30) days, the permit automatically expires and the permit fee and the proceeds of all the bonds are forfeited to the village under section 21.323. If the owner shows good cause, the director of community development or a duly authorized agent can reinstate the permit with a further payment of an additional permit fee. An applicant must also obtain the permit within thirty (30) days after written notice of approval, or the application is voided. The village manager can issue a permit with an expiration date beyond one year, but never longer than two (2) years.

Fees are handled in a separate section. Section 21.305 says the fees for the installation, alteration or extension of a plumbing system are set out in appendix A, division II of the Code, while fees for new water mains, water main extensions and water services are described in chapter 15, article VIII. Section 21.317 adds a reinspection fee, paid by the general contractor listed on the permit, when a second or subsequent inspection is needed for the same code deficiency.

The technical standard is the Illinois State Plumbing Code, 77 Illinois Administrative Code 890, adopted in its entirety by section 21.105 with local amendments. Those amendments require vaults for flood control systems to be a minimum of 60 inches in diameter, a full size cleanout on the street side of the vault, and ASME/ANSI listed backwater valve assemblies. Where a building has plumbing fixtures below grade, the sewer runs overhead and the fixtures drain to an approved sanitary ejector pit. Alterations or remodeling of existing basement plumbing with gravity sewers require an overhead installation connecting the ejector pump discharge into the soil stack at a height of seven feet (7') above the floor. New plumbing fixtures and irrigation controllers must bear the WaterSense label when labeled fixtures are available.

Violations & Fines

Under section 21.403A, anyone violating chapter 21 is fined the amount set in appendix A, division III for each offense, and each day a violation continues is a separate offense. Under section 21.403C, if work starts without a permit the specified permit fee is doubled, and paying it does not relieve the person of other penalties. Section 21.403B also lets the village go to court to restrain, correct or abate the violation or to prevent occupancy of the building.

Frequently Asked Questions

Do I need a permit to change plumbing in the Village of Mount Prospect?
Yes. Section 21.203 makes it unlawful to make any change in plumbing, heating or electrical piping, air conditioning or appurtenance before the proper permits have been obtained from the department of community development. The rule reaches alteration and repair work as well as new construction, so a replacement job needs the same permit as a new installation.
How long does a plumbing permit last?
Under section 21.203B, construction must start within sixty (60) days after the permit is issued and be carried to completion within one year. The permit automatically expires if work stops for a period of thirty (30) days. The village manager can issue a permit with a later expiration date, but never longer than two (2) years.
What happens if plumbing work starts before the permit is issued?
Section 21.403C doubles the specified permit fee when any work has commenced without a permit, and the minimum and maximum penalty for each category of unauthorized work is set in appendix A, division III. Paying the doubled fee does not relieve the person of any other requirement or penalty prescribed in chapter 21.
Which plumbing code does the Village of Mount Prospect enforce?
Section 21.105 adopts the Illinois State Plumbing Code, 77 Illinois Administrative Code 890, promulgated by the Illinois Department of Public Health, in its entirety except for the local amendments. Those amendments cover flood control systems, backwater valves, approved piping materials, sanitary ejector pits and the WaterSense label for new fixtures.

Sources & Official References

Other rules in Mount Prospect

All Mount Prospect rules

Compare Mount Prospect to another location·View the Illinois building safety overview

Get notified when Plumbing Permits in Mount Prospect, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Nearby Cities

How other cities in Cook County handle plumbing permits.

Evanston, IL
Some Restrictions
Chicago, IL
Some Restrictions
Tinley Park, IL
Some Restrictions
Oak Lawn, IL
Some Restrictions
Schaumburg, IL
Some Restrictions
Oak Park, IL
Some Restrictions
Skokie, IL
Some Restrictions
Arlington Heights, IL
Some Restrictions