Key Facts

Governing section
Dallas City Code Sec. 19-118.6
Plan required
Stormwater Pollution Prevention Plan (SWPPP) to director
Duration of duty
Until final stabilization and notice of termination
Liable parties
Owner and operator jointly and severally responsible
Enforcement tool
City may deny or revoke building/grading permits
Penalty
$250-$2,000 per day, Sec. 19-118.1

Summary

Every construction site in Dallas that disturbs soil has to install erosion and sediment control best management practices before work starts and keep them running until the site is fully stabilized, under City Code Sec. 19-118.6. The rule ties directly into the city's NPDES/TPDES stormwater permit and makes owners jointly liable with contractors.

(a) An operator of a construction site shall comply with all terms and conditions of a construction general permit or an individual permit, whichever is obtained for or applicable to the construction site. An operator of a construction site shall provide the director with a copy of the stormwater pollution prevention plan required by the construction general permit or individual permit and shall implement best management practices to control and minimize the discharge into the stormwater drainage system, waters of the United States, and state water of any sediment, silt, earth, soil, or other material from the construction site. Erosion control elements meeting the criteria for best management practices must be installed before any construction site is established in accordance with an installation schedule as specified in a stormwater pollution prevention plan. ... (c) The operator of a construction site is responsible for the installation and maintenance of stormwater management measures until final stabilization of the site has been completed and the notice of termination has been received by the director. (g) An owner of a construction site is jointly and severally responsible with the operator for compliance with the requirements of this section, even if the owner is not an operator of the site.

Source: Dallas City Code Sec. 51A-5.207 – Grading Plan (Chapter 51A Development Code)View official code

Full Breakdown

Sec. 6(a) requires an operator of a construction site to comply with the construction general permit or individual TPDES/NPDES permit that applies to the site, hand the director a copy of the required stormwater pollution prevention plan (SWPPP), and implement best management practices to control sediment, silt, earth, and soil before any construction site is established, on the installation schedule set in the SWPPP. Subsection (b) lists more than a dozen specific measures the SWPPP can require: preserving existing vegetation and stabilizing disturbed soil with temporary or permanent seeding, mulching, geotextiles, or sod as soon as work stops in a given area; diverting flows away from exposed soil; limiting sediment tracking and dust off-site; keeping cement, concrete washout water, and mortar out of the drainage system; containing spills of paint, solvent, and fuel; and, for any on-site concrete batch plant, building continuous interior berms around mixing equipment, truck loading areas, and washout facilities with lined containment.

Subsection (c) keeps the operator on the hook for maintaining these measures until final stabilization of the site has been completed and the notice of termination has been received by the director, not merely until construction wraps. Subsection (f) gives the city real teeth: it can deny a building permit, grading permit, subdivision plat, or other city approval if the submitted plans, or what the director observes on a site inspection, do not control sediment discharge to the maximum extent practicable. Liability is shared broadly under Subsections (g) and (h): the property owner is jointly and severally responsible with the operator even if the owner never operates the site, and any contractor or subcontractor tasked with a specific control measure is jointly and severally liable if a negligent or willful failure to implement it causes a water quality violation.

Violations & Fines

A construction site that skips required erosion control measures, or fails to maintain them until final stabilization, violates Sec. 19-118.6 and the broader prohibited-discharge rule in Sec. 19-118.2(g). Sec. 19-118.1(c) makes each day of noncompliance a separate offense, fined $250 to $2,000, and the director can deny or revoke a building, grading, or plat approval until the site's best management practices are corrected, in addition to any state TCEQ enforcement under the site's TPDES permit.

Frequently Asked Questions

Does a Dallas construction site need an erosion control plan?
Yes, if it disturbs soil under a TPDES or NPDES construction permit. Sec. 19-118.6(a) requires the operator to give the director a copy of the stormwater pollution prevention plan and install erosion control best management practices before the site is established, on the schedule set in that plan.
Who is liable if a Dallas construction site causes erosion violations?
More than just the contractor on the ground. Sec. 19-118.6(g) makes the property owner jointly and severally responsible with the operator even if the owner never runs day-to-day operations, and Subsection (h) extends liability to any subcontractor whose negligent or willful failure to implement an assigned control measure causes a water quality violation.
Can Dallas deny a building permit over inadequate erosion control?
Yes. Sec. 19-118.6(f) lets the city deny a building permit, grading permit, subdivision plat, or other development approval if the erosion and sediment control measures shown in the plans, or observed during a site inspection, do not reduce sediment discharge to the maximum extent practicable.

Sources & Official References

Other rules in Dallas

All Dallas rules

Texas rules heatmap·Compare Dallas to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Dallas, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Dallas County handle erosion control.

Cedar Hill, TX
Light Restrictions
DeSoto, TX
Light Restrictions
Garland, TX
Light Restrictions
Carrollton, TX
Some Restrictions
Richardson, TX
Some Restrictions
Grand Prairie, TX
Some Restrictions
Irving, TX
Some Restrictions