Caldwell, ID Environmental Rules: Stormwater Management (2026)
Key Facts
- SWPPP required for
- sites disturbing 1+ acre
- Plan filed with
- Caldwell Stormwater Division
- State permit needed
- Idaho DEQ Construction General Permit
- Plan preparer
- must be a qualified person
- Major plan changes
- reviewed like original plan
- IPDES discharge penalty
- up to $1,000
Summary
Any Caldwell development disturbing one acre or more must have a Stormwater Pollution Prevention Plan approved by the Caldwell Stormwater Division before a grading permit issues, and the developer must separately secure Construction General Permit coverage from the Idaho Department of Environmental Quality.
(1) Contents: The stormwater pollution prevention plan (SWPPP) shall include: A. A sequence of construction of the development site, including stripping and clearing, rough grading, stockpiling, construction of utilities, infrastructure, and buildings, and final grading and landscaping. Sequencing shall identify the expected date on which clearing will begin, the estimated duration of exposure of cleared areas, and the sequence of clearing, installation of temporary erosion and sediment measures, and establishment of permanent vegetation. B. All erosion and sediment control measures necessary to meet the objectives of this article throughout all phases of construction and permanently, after completion of development of the site. (2) Preparation By Qualified Person: The erosion and sediment control plan must be prepared by a qualified person.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 Code: Local legislation current through Ordinance 3747, passed 3-16-2026).
Full Breakdown
Under § 04-19-07, no grading permit for uncovering one acre or more of land issues without a SWPPP approved by the Caldwell Stormwater Division, and any development site over one acre, or part of a larger development plan, must file its SWPPP with the Division and obtain Construction General Permit (CGP) coverage through the Idaho Department of Environmental Quality. Section 04-19-09 spells out what the plan must contain: a construction sequence covering stripping, clearing, rough grading, stockpiling, utility and building construction, and final grading and landscaping, identifying the expected clearing start date, how long cleared areas will stay exposed, and the order of clearing, temporary control installation and permanent vegetation establishment.
The plan must also list every erosion and sediment control measure needed throughout construction and permanently afterward, and it must be prepared by a qualified person. Minor field modifications can be authorized in writing by the Caldwell Public Works Department, but changes the Department considers major must go through the same review and approval process as the original plan (§ 04-19-09). The permittee or their agent must make regular inspections of every control measure on the schedule set in the approved plan or permit and submit written inspection reports to the Stormwater Division, which can also enter the property to inspect directly (§ 04-19-13).
Violations & Fines
Undertaking regulated activity without a current, valid SWPPP-backed permit, or violating the terms of an issued permit, lets the City Stormwater Division issue a stop work order and suspend or revoke the grading permit, alongside monetary penalties (§ 04-19-15). Discharging pollution to Idaho waters or waters of the United States in violation of the City's IPDES permit carries penalties up to $1,000 and possible misdemeanor charges, and any Article 19 violation is punishable under Idaho Code §§ 50-302(1) and 18-113 as a misdemeanor, with each day of continued violation a separate offense.
Frequently Asked Questions
Who approves a SWPPP in Caldwell?
Do I need a state permit too, not just a city one?
What must a Caldwell SWPPP include?
Can I make changes to an approved SWPPP mid-project?
Sources & Official References
Other rules in Caldwell
Compare Caldwell to another location·View the Idaho environmental rules overview