Eagan, MN Environmental Rules: Stormwater Management (2026)
Key Facts
- Trigger
- 10,000+ sq ft new/reconstructed impervious surface
- Volume retention
- 1.1 inches of runoff retained on site
- Linear projects
- 0.55 in. or 1.1 in. net increase, larger governs
- Oil/grease control
- Required at 40+ parking stalls or drive-thrus
- Maintenance
- Annual private-facility inspection required
Summary
New development and redevelopment in Eagan that creates 10,000 square feet or more of impervious surface must retain 1.1 inches of runoff on site under City Code § 4.34(F), control peak runoff rates, and add oil and grease treatment at sites with 40 or more parking stalls.
F.Post-construction stormwater management requirements. In connection with any project for which a permit is required under this section that results in the addition of 10,000 square feet or more of new or fully reconstructed impervious surface on the site, the following post-construction/activity stormwater management requirements shall be met on the site:1.Stormwater volume control.a.New, nonlinear developments. For a new, nonlinear development that creates 10,000 square feet or more of new impervious surface on sites without infiltration restrictions, stormwater runoff volumes shall be controlled and the post-construction runoff volume shall be retained on the site for 1.1 inches of runoff from impervious surfaces. ... G.Oil and grease control. The first 1.1 inches of runoff shall be treated using effective oil and grease removal technology. Site must provide oil and grease control when the site has 40 or more parking stalls, has high traffic areas (such as drive thru windows/lanes), or commercial/business activities will take place that have the potential for oil and/or grease pollution (e.g., gas/service stations).
Full Breakdown
Eagan's stormwater management ordinance, City Code § 4.34, imposes post-construction requirements on any project needing a permit under the section that adds 10,000 square feet or more of new or fully reconstructed impervious surface. Under § 4.34(F)(1)(a), new nonlinear development must retain on site 1.1 inches of runoff calculated from the impervious surface created, and § 4.34(F)(1)(b) applies the same 1.1-inch retention standard to redevelopment and reconstruction projects. Linear projects such as roadways, sidewalks and trails must capture the larger of 0.55 inches of runoff from new impervious surface or 1.1 inches from the net increase in impervious area.
Where infiltration is restricted, for example near contaminated soils, drinking-water source areas, or high-infiltration-rate soils, an applicant must work through a three-step alternative design sequence before the city will approve a different approach. Section 4.34(F)(3) also sets rate control standards: on-site facilities must maintain predevelopment peak runoff rates for the 50 percent, ten percent and one percent probability 24-hour storm events, calculated under NOAA Atlas 14 rainfall data and the NRCS TR-55 methodology. Section 4.34(G) requires oil and grease removal technology on the first 1.1 inches of runoff at any site with 40 or more parking stalls, high-traffic areas like drive-through lanes, or businesses such as gas or service stations with grease or oil pollution potential.
Property owners must maintain private stormwater facilities under § 4.34(I), including an annual inspection by a qualified person and removal of accumulated sediment, and sign a recorded stormwater management agreement before the city issues a permit. Violating these standards is a misdemeanor under § 4.34(J), with the city able to order corrective work and recover its costs.
Violations & Fines
A property owner or developer who fails to build or maintain the required stormwater volume control, rate control or oil-and-grease treatment violates City Code § 4.34 and commits a misdemeanor under § 4.34(J). The city can order abatement, revoke permits or approvals issued in connection with the project, and recover the cost of any corrective work it performs from the violator.
Frequently Asked Questions
When does Eagan require a stormwater management permit?
How much stormwater runoff must a new Eagan development retain on site?
Does Eagan require oil and grease treatment for stormwater?
Sources & Official References
Other rules in Eagan
Compare Eagan to another location·View the Minnesota environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.